  05/08/13

Paving on US 70 east of Globe starting May 14

  04/11/13

Paving on State Route 260 in White Mountains starting April 22

  10/25/12 Drainage improvement work starting on US 180 south of Nutrioso
  10/24/12 Parking lot improvements at Boyce Thompson Arboretum State Park starting Oct. 24
  07/16/12 Project to repave State Route 77 from Shumway through Snowflake starting July 23
  06/05/12

Project to resurface SR 260 west of Show Low starting June 18


State Route 77 Taylor/Snowflake

     
  Project #'s:

077 NA 357 H766701C
077-B-(206)A

077 NA 352 H766801C
077-B-(207)A
  Location: SR 77 Mileposts 352-361.6
  Contractor: Sunland, Inc. Asphalt & Seal Coating
  Programmed Cost: $5,032,000.00
  Scope: Remove and replace asphalt, sidewalk ramps, guardrail and install new road striping
  Expected Duration: Start July 2012 and complete Summer 2013
     

SR 260 McNary to Sunrise turnoff

  Project No.: 260 AP 360 H788101C 260-C-(207)T
  Location:
SR 260 Mileposts 360-378
  Contractor: Sunland, Inc. Asphalt & Seal Coating
  Programmed Cost: $5,590,000.00
  Scope: Milling old pavement and replacing it with new, chip seal and some guardrail replacement.
  Expected Duration: Start April 2013 and complete June 2013
     

SR 260 Pierce Wash Bridge

  Project No.: 260 NA 310 H801201C 260-B-(209)T
  Location: SR 260 Mileposts 310 (Pierce Wash Bridge)
  Contractor: Show Low Construction, INC
  Programmed Cost: $121,421
  Scope: Constructing concrete floors, a rail bank and some shotcrete work for erosion control.
  Expected Duration: Start May 2013 and complete July 2013
     

US 70 Globe Lordsburg Highway (Point of Pines)

  Project No.: 070 GH 275 H788201C 070-A-(213)T
  Location: US 70 Mileposts 275-279.5 (Point of Pines Junction Area)
  Contractor: CKC Construction & Materials LLC
  Programmed Cost: $1,804,438
  Scope: Milling up old asphalt and replacing with new and new guardrails.
  Expected Duration: Start May 2013 and complete August 2013
     

US 191 KP Cienega to Beaver Head

  Project No.: 191 GE 225 H835101C 191-C-(213)T
  Location: US 191 Mileposts 225-239 (Hannigan Meadow area)
  Contractor: International Surfacing Systems
  Programmed Cost: $623,983
  Scope: Applying a full road width slurry seal to preserve the pavement.
  Expected Duration: Start June 2013 and complete July 2013
     