| Statewide Dynamic Message Sign Boards/ Phase 8 |
| |
Project No.: |
999 SW 000 H699201C 999-A-NFA (Statewide project being administered by the Flagstaff District) |
| |
Location: |
Two signs will be located on SR 89A (N Sedona and Fairgrounds in Flagstaff) and US 89 MP 462.7NB at Cameron. Two signs will be put in the Yuma District, One in the Tucson District and One in the Holbrook District. |
| |
Contractor: |
CS Construction Inc. |
| |
Programmed Cost: |
$1,068,725 |
| |
Scope: |
Install new Dynamic message board signs. |
| |
Expected Project
Duration: |
Winter 2008 to Summer 2009 |
| |
|
|
Transwestern (Bellemont) Bridge Deck Repair |
| |
Project No.: |
040 CN 185 H7838 01C |
| |
Location: |
Transwestern Bridge deck which crosses I-40 at Bellemont and Camp Navajo |
| |
Contractor: |
DBA Construction |
| |
Programmed Cost: |
$258,000 |
| |
Scope: |
Mill the bridge deck and then cover it with a microsilica concrete overlay. |
| |
Expected Project
Duration: |
August 2009 to September 2009 |
| |
|
|
I-40 Micro Seal Milepost 150 to 191 |
| |
Project No.: |
040 CN 150 H784501C ARRA-040-C(203)A |
| |
Location: |
I-40 from milepost 150 to 191 |
| |
Contractor: |
Southwest Slurry Seal, Inc. |
| |
Programmed Cost: |
479,104.50 |
| |
Scope: |
Apply micro seal treatment to 41 miles of I-40. |
| |
Expected Project
Duration: |
Summer 2009 to Fall 2009. |
| |
|
|
I-40 Shoulder Rehabilitation MP 177-190.4 |
| |
Project No.: |
040 CN 177 H751401C 040-C(200)A; 040 CN 182 H768901C 040-C(201)A |
| |
Location: |
I-40 milepost 177 to 182 both EB and WB shoulders and milepost 182 to 190.4 just the WB shoulder. |
| |
Contractor: |
Combs Construction Company |
| |
Programmed Cost: |
$497,463.52 |
| |
Scope: |
Mill 1/2" of asphalt and replace with new on the roadway shoulders. Put in rumble strip and apply new paint stripe. |
| |
Expected Project
Duration: |
Summer 2009 to Fall 2009 |
| |
|
|
I-40 Walnut Canyon Westbound |
| |
Project No.: |
40 CN 205 H545701C ARRA-040-E(202)A |
| |
Location: |
Project is westbound only from MP 209.1 to MP 205.1. The Cosnino Interchange is located within this project. |
| |
Contractor: |
C.S.&W. Contractors, Inc. |
| |
Programmed Cost: |
$5,809,917.48 |
| |
Scope: |
Reprofile the vertical curves. This involves taking out some of the small grades. |
| |
Expected Project
Duration: |
Project will run into the fall of 2009 at which time it will stop. It will be resumed and completed Spring 2010. |
| |
News Release: |
ADOT to close westbound I-40 ramps at Cosnino Road ~ June 24, 2009 |
| |
|
|
SR 64 to Volunteer Wash |
| |
Project No.: |
040 CN 166 H780801C ARRA-040-C(202)A |
| |
Location: |
On both sides of I-40 from mile post 166 to 174 and 183 to 188. |
| |
Contractor: |
American Fence Company of Arizona Inc. |
| |
Programmed Cost: |
287,411.30 |
| |
Scope: |
Removal of barbed wire fence and install new barbed wire game fence on both sides of the freeway. |
| |
Expected Project
Duration: |
Summer 2009 to Winter 2009 |
| |
|
|
| SR 89A Continuous Highway Lighting |
| |
Project No.: |
89A YV 371 H7130 01D, HES A89-B(202) |
| |
Location: |
SR 89A from milepost 371 to 373 |
| |
Contractor: |
Not bid yet |
| |
Programmed Cost: |
Current estimate $2,000,000 |
| |
Scope: |
Install continuous highway lighting and traffic signal at Andante. |
| |
Expected Project Duration: |
Projected for Fall 2010 to Spring 2011 |
| |
Project Documents: |
Sedona Pedestrian Crossing Study |
| |
|
Highway Enhancements for Safety Report |
| |
|
Funding Approval |
| |
|
Revised Funding Approval |
| |
|
Final Project Assessment |
| |
|
Final Lighting Design Criteria Report |
| |
|
Presentation to Sedona City Council October 28, 2009 |
| |
|
Public Information Packet on Lighting System Alternatives |
| |
|
Public Comment Form |
| |
|
Information on Nighttime Lighting |
| |
|
|
| SR 179 Village of Oak Creek to Y (Project 1 and 2) |
| |
Project No.: |
STP-TEA-A(001)B and STP-TEA-A(002)B |
| |
Location: |
Project 1 is from MP 304.5 (1 mile south of Village of Oak Creek) to MP 310.4 (Back o’ Beyond) and
Project 2 is from MP 310.4 to 313.4 (the “Y”) in the City of Sedona. |
| |
Contractor: |
Southwest Asphalt Paving (Project 1) |
| |
Programmed Cost: |
Project 1 $36,114,000
Project 2 $51,750,000 |
| |
Scope: |
Projects consist of complete rebuild of highway to a multimodal, two lane parkway. |
| |
Expected Project Duration: |
Project 1 Completed
Project 2 Spring 2008 to Spring 2010 |
| |
|
|
US 160 from the Junction of US 89 to Van’s Trading Post |
| |
Project No.: |
160 CN 311 H527401C ARRA-160A(001)A |
| |
Location: |
Project is on US 160 and starts at the junction of US 89. Project moves east on US 160 and ends at Van’s Trading Post mile post 320. |
| |
Contractor: |
Granite Construction Company |
| |
Programmed Cost: |
$2,947,263.30 |
| |
Scope: |
Removal of existing asphalt by milling and then replacing with new. Also includes shoulder build-up, new guardrail, pavement markings and seeding. |
| |
Expected Project Duration: |
Summer 2009 to Fall 2009 |
| |
|
|
US 89 North of Flagstaff (Townsend Road to Fernwood) |
| |
Project No.: |
089 CN 420 H682601C ARRA-089C(200)A |
| |
Location: |
Project is on US 89 just north of the Flagstaff city limits. Project runs from mile post 420.33 to mile post 425.78. |
| |
Contractor: |
Meadow Valley Contractors, Inc. |
| |
Programmed Cost: |
$3,652,195.40 |
| |
Scope: |
Removal of existing asphalt by milling and then replacing with new. Also includes installing loop traffic counter system, pavement markings and signage. |
| |
Expected Project Duration: |
Summer 2009 to Fall 2009 |
| |
|
|