SR 89A Roadway and Safety Improvements

   

Project Overview
The Arizona Department of Transportation will repave more than three miles of State Route 89A in Sedona from Arroyo Piñon Dr. to just west of SR 179, install a traffic signal at Andante Drive, and install roadway lighting from Dry Creek Road to Airport Road.

What to Expect:

  • Initial work will begin in mid to late January
  • The plan is to construct the roadway lighting first, followed by the traffic signal, and then the paving in late spring and summer
  • The lighting and traffic signal work will be done during the day and the paving work will be done at night
  • The initial traffic impacts will be minimal; there will be lane restrictions while the roadway is being repaved
  • The project is scheduled for completion by late summer.

There is a possibility that unscheduled closures or restrictions may occur due to weather and other unforeseen circumstances.