Thursday, August 25, 2011

Westbound HOV lanes on Loop 101 aren't open yet, but they will be soon

The Loop 101 HOV project is more than 80 percent complete. By November
all 30 miles of new HOV lanes will be open along the Loop 101.
If you live and drive the Loop 101 in the West and North Valley you probably noticed the first stretch of HOV lanes on the eastbound Loop 101 recently opened. These new lanes already have helped to ease congestion in the North Valley, especially during the morning commute.

You may have also noticed that the westbound HOV lanes appear to be done as well, but are not opened. ADOT has not decided to taunt you – these lanes aren’t open yet for a reason.

A little background on the project...
The Loop 101 HOV lane project will add 30 miles of HOV lanes along Loop 101 from I-10 to SR 51.

ADOT already has added HOV lanes to Loop 101 in the East Valley between SR 51 and Loop 202  during the past three years. The completion of final 30 miles in the West Valley will give drivers more than 60 miles of uninterrupted HOV access!

Why the westbound lanes aren't open yet...
When the first stretch of HOV lanes on the current project was opened it was because the new HOV lanes did not come to an end, but rather connected to the existing lanes east of SR 51. This enabled ADOT to open the first few miles of the new HOV lanes on the eastbound Loop 101.

So, although it appears as though the westbound Loop 101 HOV lanes between SR 51 and 7th Avenue (as well as other areas along the westbound Loop 101) will soon be ready to open, ADOT will not open these lanes until the rest of the project is completed.

We do not want to open a smaller stretch of HOV lanes that will simply come to an end and cause traffic to merge unnecessarily, just for the sake of opening lanes. We would rather hold off and open the lanes when they are completed so that traffic is not forced to merge where the smaller sections of HOV lanes end.

However, we have opened auxiliary lanes on both the east and westbound Loop 101 between Cave Creek Road and SR 51. These lanes help to improve the flow of traffic along this very busy section of the Loop 101 where traffic is merging either onto or from SR 51. Since opening, there is a noticeable difference along this section of the Loop 101.

The good news is this project is more than 80 percent complete. By November, all 30 miles of new HOV lanes will be open along the Loop 101 allowing motorists to enjoy a much easier ride in both the West and North Valley!
Posted by Angela DeWelles   |  Labels:  Construction, HOV-Lanes, Loop-101, Valley-Freeways, Valley-Freeways-Thursday


Civil RightsTitle VI of the Civil Rights Act of 1964, and the Americans with Disabilities Act (ADA)
  • Pursuant to Title VI of the Civil Rights Act of 1964, and the Americans with Disabilities Act (ADA), ADOT does not discriminate on the basis of race, color, national origin, age, sex or disability. Persons that require a reasonable accommodation based on language or disability should contact ADOT’s Civil Rights Office at 602.712.8946 or at Requests should be made as early as possible to ensure the State has an opportunity to address the accommodation.
  • De acuerdo con el título VI de la Ley de Derechos Civiles de 1964 y la Ley de Estadounidenses con Discapacidades (ADA por sus siglas en inglés), el Departamento de Transporte de Arizona (ADOT por sus siglas en inglés) no discrimina por raza, color, nacionalidad, edad, género o discapacidad.  Personas que requieren asistencia (dentro de lo razonable) ya sea por el idioma o por discapacidad deben ponerse en contacto con la Oficina de Derechos Civiles al 602.712.8946 o en Las solicitudes deben hacerse lo más pronto posible para asegurar que el equipo encargado del proyecto tenga la oportunidad de hacer los arreglos necesarios.