Thursday, July 17, 2014

US 89 landslide repairs to begin later this month

The truck to the left is capable of hauling about 23 cubic yards of material per load.Try to visualize what one million cubic yards of rock and dirt amounts to…

That’s the quantity of material expected to be removed by crews as they work to repair US 89, the landslide-damaged highway just south of Page.

It’s hard to picture, isn’t it?

Help your imagination out by taking a look at the photo at right. We’re told these yellow trucks (the pickup truck on the right is there for scale) are capable of hauling about 23 cubic yards of material per load. So, with nearly one million cubic yards to move, it will take approximately 43,500 truckloads to finish the job … that’s a lot of rocks!

Work to start soon
Crews will begin moving those rocks very soon. The reconstruction of US 89 between Bitter Springs and Page is set to begin later this month. The State Transportation Board approved the $25 million project to repair the highway at their July 11 meeting in Cottonwood.

The roadway, which suffered catastrophic damage following a landslide on the early morning of Feb. 20, 2013, has remained closed after a 500-foot section of roadway buckled in Echo Cliffs, approximately 25 miles south of Page.

More about the necessary repairs
The project will include moving the roadway approximately 60 feet away from the landslide area toward Echo Cliffs and using rock material removed for the roadway realignment to construct a downslope buttress to stabilize the area.

The closed section of roadway is scheduled to reopen prior to next summer’s busy travel season. The construction contract will include a monetary incentive for the contractor if it is able to complete the project ahead of schedule.

Work on the project begins in a couple of weeks, but the major work is expected to start in late August when crews begin drilling and blasting operations to build the rock buttress.

The ultimate repair of US 89 is the final step in fulfilling ADOT’s three-pronged approach to the US 89 landslide incident, which included providing immediate emergency access, conducting a geotechnical investigation and restoring essential traffic to the area. 

Last summer ADOT paved Navajo Route 20 (Temporary US 89), which was a mostly dirt road stretching from Bodaway-Gap to LeChee.

“Once a long-term solution was identified, ADOT worked diligently to complete all the federally required clearances needed prior to construction,” said Steve Boschen, ADOT deputy state engineer of project delivery. “This process can sometimes take years, but with help from many of our Navajo Nation partners, the Federal Highway Administration and other regulatory stakeholders, we are ready to begin the US 89 landslide repair.”

If you’ve been following along with us here on the blog, you’ll remember that ADOT has had several hurdles to clear up to this point. After an extensive geotechnical investigation identified the necessary repairs last summer, ADOT retained an engineering design firm and developed plans for the eventual repair. Following that, the team finalized all federally required environmental reviews that include cultural, biological and water quality measures, completed the plans for the required right-of-way easements, and finalized negotiations with the contractor.

The final step prior to last week’s board approval was completing negotiations on a guaranteed maximum price for the project construction with FNF Construction, the same contractor that completed the paving of US 89T.

The US 89 landslide repair project is eligible for reimbursement through the Federal Highway Administration’s emergency relief program, which provides funding to state and local agencies for the repair or reconstruction of highways, roads and bridges that are damaged in natural disasters and catastrophic failures.

Stay up-to-date by visiting You’ll also want to stay tuned to the ADOT Blog for updates – we plan on giving you a very up-close look at the repairs.
Posted by Angela DeWelles   |  Labels:  US-89


Civil RightsTitle VI of the Civil Rights Act of 1964, and the Americans with Disabilities Act (ADA)
  • Pursuant to Title VI of the Civil Rights Act of 1964, and the Americans with Disabilities Act (ADA), ADOT does not discriminate on the basis of race, color, national origin, age, sex or disability. Persons that require a reasonable accommodation based on language or disability should contact ADOT’s Civil Rights Office at 602.712.8946 or at Requests should be made as early as possible to ensure the State has an opportunity to address the accommodation.
  • De acuerdo con el título VI de la Ley de Derechos Civiles de 1964 y la Ley de Estadounidenses con Discapacidades (ADA por sus siglas en inglés), el Departamento de Transporte de Arizona (ADOT por sus siglas en inglés) no discrimina por raza, color, nacionalidad, edad, género o discapacidad.  Personas que requieren asistencia (dentro de lo razonable) ya sea por el idioma o por discapacidad deben ponerse en contacto con la Oficina de Derechos Civiles al 602.712.8946 o en Las solicitudes deben hacerse lo más pronto posible para asegurar que el equipo encargado del proyecto tenga la oportunidad de hacer los arreglos necesarios.