Interstate 17 and JW Powell Traffic Interchange Improvements

An improvement project to reconstruct the interchange at I-17 and JW Powell Boulevard has begun.

The improvement project will realign State Route 89A / Beulah Boulevard in the vicinity of Fort Tuthill County Park and construct two roundabouts, one at the entrance of the park and the other at the I-17 southbound ramps, to provide a safer transition for traffic through the intersections.

Timeline
  • Trees thinned in project area: September 2013
  • Winter shutdown: October to February 2013-2014 and 2014-2015
  • Construction begins: June 2014
  • Anticipated completion: Summer 2015