Northwest Regional Improvements US 93 and I-40

Northwest Regional Improvements US 93 and I-40

Contents

ADOT has more than 20 current and upcoming projects on the Interstate 40 and US 93 corridors across northwestern Arizona. The improvements include 48 miles of new pavement on I-40, and 84 miles of new pavement on US 93. There are also several projects that will widen the existing 2-lane roadway into a four-lane divided highway.

Northwest Regional Improvements US 93 Trailhead
Northwest Regional Improvements US 93 Highway Photo

US 93 Northwest Regional Improvements

US 93 Improvements

View Map: US 93 Improvements

Project: Legend Ranch Road - Date Creek Road Pavement Repair
Project Elements: Completed in 2024: Repair two segments of pavement on US 93 in Mohave County, mileposts 59 to 70 and 95 to 97.
More info: https://azdot.gov/projects/northwest-district-projects/us-93-legend-ran…
Project map: Legend Ranch Road - Date Creek Road Pavement Repair Project Map
Click map to enlarge
Project: Sanctuary Road to I-40
Project Elements: Remove and replace the existing pavement and other improvements along a 23-mile segment of US 93 near Chloride, mileposts 48 to 71. Schedule: Construction is expected to start in summer 2025 and be completed in late 2025
More info: https://azdot.gov/projects/northwest-district-projects/us-93-corridor-p…
Project: Cane Springs Improvements
Project Elements: Widen a 4-mile segment of US 93 from a two-lane undivided roadway to a 4-lane divided highway north of the community of Wikieup, between mileposts 106 and 110. Schedule: Construction is expected to begin in late 2024 and be complete in 2026.
More info: https://azdot.gov/projects/northwest-district-projects/us-93-cane-springs-improvement-project
Project map: Cane Springs Improvements Project Map
Click map to enlarge
Project: Gunsite Canyon Road - Gray Wash
Project Elements: Remove and replace the top pavement surface along a 10-mile section of US 93 located between Gunsite Canyon Road and Gray Wash in the community of Wikieup. Schedule: Construction started in March 2024 and is expected to be completed in summer 2024.
More info: https://azdot.gov/projects/northwest-district-projects/us-93-pavement-project-gunsite-canyon-rd-to-gray-wash
Project map: Gunsite Canyon Road - Gray Wash Project Map
Click map to enlarge
Project: E. Oldeup Road to 17 Mile Road
Project Elements: Remove and replace the existing top pavement along a 13-mile section of US 93 near Wikieup, mileposts 131 to 144. Schedule: Construction is expected to begin and be completed in 2025.
Project: Nothing - State Route 97
Project Elements: Remove and replace the existing top pavement along a 12-mile section of roadway, roughly between the community of Nothing and State Route 97, mileposts 144 to 156. Schedule: Work will resume in spring 2024 and is expected to be completed summer
More info: https://azdot.gov/projects/northwest-district-projects/us-93-mohave-county-nothing-and-state-route-97
Project map: Nothing - State Route 97 Project Map
Click map to enlarge
Project: Big Jim Wash Improvements
Project Elements: Construct one additional lane in each direction and improve this 4-mile segment of US 93 to a 4-lane divided highway south of the community of Nothing, mileposts 162 - 166. Project Schedule: Construction is expected to begin in 2026.
More info: https://azdot.gov/projects/northwest-district-projects/us-93-corridor-projects
Project: Passing Lanes
Project Elements: Construct passing lanes near Wickenburg (mileposts 172-173 and 176-177). Schedule: Construction is expected to begin in 2026.
More info: https://azdot.gov/projects/northwest-district-projects/us-93-corridor-projects
Project: Moore Ranch Road- Milepost 190
Project Elements: Remove and replace the existing top pavement along a 13-mile section of US 93 north of Wickenburg. Schedule: Paving is scheduled for 2024.
More info: https://azdot.gov/projects/northwest-district-projects/us-93-corridor-projects
Project: Vista Royale Improvements
Project Elements: Construct one additional lane in each direction and improve this 3.5-mile segment of US 93 to a 4-lane divided roadway. Schedule: ADOT has applied for a federal grant to fund the design and construction for the US 93 Vista Royale improvements.
More info: https://azdot.gov/projects/northwest-district-projects/us-93-vista-royale-improvements
Project map: Vista Royale Improvements Project Map
Click map to enlarge
Project: Tegner Street - Wickenburg Ranch Way Improvements
Project Elements: Construct one additional lane in each direction and improve this 5-mile segment of US 93 to a 4-lane divided roadway in Wickenburg, mileposts 194 to 199. Schedule: Construction began spring 2023. The project will be constructed over two years.
More info: https://azdot.gov/projects/northwest-district-projects/us-93-tegner-street-wickenburg-ranch-way
Project map: Tegner Street - Wickenburg Ranch Way Improvements Project Map
Click map to enlarge

i-40 Northwest Regional Improvements

Interstate 40 Improvements

View Map: I-40 Improvements

Project: AZ/CA State Line - Needle Mountain Road
Project Elements: Remove and replace the top-pavement surface along a 2-mile segment of I-40 between the Arizona- California state line and Topock, mileposts 0 to 2. Schedule: Construction is expected to begin in late 2024 and finish in early 2025.
Project: Needle Mountain Road - State Route 95
Project Elements: Remove and replace the top-pavement surface along a 6-mile segment of I-40 roughly between Topock and the junction with SR 95, mileposts 2 - 8. Schedule: Construction is expected to begin in summer 2024 and be complete in fall 2024.
Project: Holy Moses Wash - Rattlesnake Wash
Project Elements: ADOT will remove and replace the top pavement surface along an 11-mile section of I-40 east of Kingman, mileposts 47-58. Schedule: Paving is expected to begin in spring 2025 and be completed in late 2025.
Project: I-40/US 93 West Kingman Traffic Interchange
Project Elements: Construct a new system-to-system traffic interchange that will create a free-flowing connection between Interstate 40 and US 93 in west Kingman. Schedule: Construction is expected to begin in summer 2024 and be completed in 2026.
Project: I-40/US 93 West Kingman Traffic Interchange
Project Elements: Construct a new system-to-system traffic interchange that will create a free-flowing connection between Interstate 40 and US 93 in west Kingman. Schedule: Construction started in July 2024 and will be completed in 2026.
More info: azdot.gov/westkingmanTI
Project map: I-40/US 93 West Kingman Traffic Interchange Project Map
Click map to enlarge
Project: Andy Devine Avenue Bridge Deck Replacement
Project Elements: Remove and replace the bridge deck on the I-40 Andy Devine Avenue Bridge (Exit 53) in east Kingman. Schedule: The project started in 2023, and is scheduled to be completed in late 2024
More info: https://azdot.gov/projects/northwest-district-projects/interstate-40-andy-devine-avenue-bridge-deck-replacement
Project map: Andy Devine Avenue Bridge Deck Replacement Project Map
Click map to enlarge
Project: Holy Moses Wash - Walnut Creek
Project Elements: Remove and replace the top pavement surface along a 13-mile section of I-40 southwest of Kingman, mileposts 33-46. Schedule: Paving is expected to begin in spring 2024 and be completed in late 2024.
More info: https://azdot.gov/projects/northwest-district-projects/interstate-40-pavement-project-holy-moses-wash-to-walnut-creek
Project map: oly Moses Wash - Walnut Creek Project Map
Click map to enlarge
Project: Willow Creek Bridge #3 Replacement
Project Elements: Remove and replace the eastbound I-40 Willow Creek Bridge #3 located between the town of Seligman and the city of Kingman. Schedule: Construction started in 2023 and is expected to be completed in late 2024.
More info: http://azdot.gov/projects/northwest-district-projects/i-40-willow-creek-bridge-3-replacement
Project map: I-40: Willow Creek Bridge #3 Replacement Project Map
Click map to enlarge
Project: Fort Rock Road - Markham Wash Bridge
Project Elements: Remove and replace the top-riding surface along a 16-mile section of eastbound I-40 between Fort Rock Road and Markham Wash Bridge, west of Seligman, mileposts 92-108. Schedule: Construction is expected to begin in the spring 2024 and be completed in late 2024.
More info: https://azdot.gov/projects/northwest-district-projects/eastbound-interstate-40-pavement-project-fort-rock-road-to-markham-wash-bridge
Project map: Eastbound Interstate 40 Pavement Project: Fort Rock Road to Markham Wash Bridge Project Map
Click map to enlarge
Project: East Seligman Bridge Deck Replacement
Project Elements: Reconstruct and replace the east- and westbound bridge decks on I-40 at exit 123 near Seligman in Yavapai County. Schedule: Construction began in 2022 and will be completed in summer 2024.
More info: https://azdot.gov/projects/northwest-district-projects/interstate-40-east-seligman-bridge-decks-replacement
Project map: Eastbound Interstate 40 Pavement Project: Fort Rock Road to Markham Wash Bridge Project Map
Click map to enlarge
Project: Ash Fork Creek Bridges
Project Elements: ADOT has initiated a bridge scour retrofit on four bridges along I-40 in the community of Ash Fork, mileposts 146. Schedule: Construction is expected to begin spring 2024 and be completed in late 2024.
More info: https://azdot.gov/projects/northwest-district-projects/i-40-ash-fork-creek-bridges
Project map: I-40 Ash Fork Creek Bridges Project Map