Mainline paving begins on South Mountain Freeway in Laveen

Twenty-two miles of new pavement needed prior to late 2019 opening
August 14, 2018

PHOENIX – You’ve got to start somewhere.PaveA

And for the Loop 202 South Mountain Freeway, “somewhere” is near Elliot Road and 59th Avenue in Laveen, where the first lane mile of pavement is in place for the state’s largest single highway project ever.

Laying pavement began in late July and has occurred in one of the flattest stretches of the South Mountain Freeway project, from north of Estrella Drive to Olney Avenue.

Mainline paving throughout the project will continue until just prior to the opening of the 22-mile freeway by late 2019. Paving will begin later this summer in the Pecos segment east of 40th Street in Ahwatukee.

“This is a huge milestone for the South Mountain Freeway project,” said Rob Samour, ADOT’s senior deputy state engineer for major projects. “The start of paving brings us that much closer to delivering traffic relief to Phoenix motorists and providing a much-needed alternative to I-10 to travel between opposite ends of the Valley.”

A 4-inch-thick asphalt base has been paved, and additional layers of pavement will follow.

To date, paving has not required any traffic restrictions.

The work involves several dump trucks delivering the asphalt, paving machines spreading it and rollers compacting it. Connect 202 Partners, the developer of the South Mountain Freeway project, can put down up to 3,500 tons of asphalt per day with a single paving pass. 

The first step toward paving is creating an embankment and compacting it to the designed height needed for the future roadway. Approximately 10 million cubic yards of earth, the equivalent of more than 800,000 truckloads and enough to fill University of Phoenix Stadium 13 times, is being hauled and compacted for the project. Once the earthwork is finished in an area, paving can begin.

Following the paving, crews will add lighting, curbs and gutters, signage and landscaping and complete other related work.

PaveCThe South Mountain Freeway, which is scheduled to open in late 2019, will provide a long-planned direct link between the East Valley and West Valley and a much-needed alternative to Interstate 10 through downtown Phoenix. Approved by Maricopa County voters in 1985 and again in 2004 as part of a comprehensive regional transportation plan, it will complete the Loop 202 and Loop 101 freeway system.

You can stay informed about the South Mountain Freeway project and sign up for updates and weekly traffic alerts at SouthMountainFreeway.com.

The Arizona Ombudsman – Citizens Aide helps you resolve ongoing issues with State Agencies.

Civil Rights

Pursuant to Title VI of the Civil Rights Act of 1964, the Americans with Disabilities Act (ADA) and other nondiscrimination laws and authorities, ADOT does not discriminate on the basis of race, color, national origin, sex, age, or disability. Persons that require a reasonable accommodation based on language or disability should contact ADOT’s Civil Rights Office at civilrightsoffice@azdot.gov. Requests should be made as early as possible to ensure the State has an opportunity to address the accommodation.

De acuerdo con el Título VI de la Ley de Derechos Civiles de 1964, la Ley de Estadounidenses con Discapacidades (ADA por sus siglas en inglés) y otras normas y leyes antidiscriminatorias, el Departamento de Transporte de Arizona (ADOT) no discrimina por motivos de raza, color, origen nacional, sexo, edad o discapacidad. Las personas que requieran asistencia (dentro de lo razonable) ya sea por el idioma o discapacidad deben ponerse en contacto con la Oficina de Derechos Civiles de ADOT en civilrightsoffice@azdot.gov. Las solicitudes deben hacerse lo más antes posible para asegurar que el Estado tenga la oportunidad de hacer los arreglos necesarios.