Saturday night’s all right for working

Ina Road Bridge

By Tom Herrmann / ADOT Communications

Holiday parties? On the last pre-holiday weekend of the year?

No, thanks. There’s work to do.

While some of us might get an early start on the Christmas and New Year’s holidays waiting for us over the next two weekends, Arizona Department of Transportation crews at Ajo Way and Ina Road will be firming up their credentials for Santa’s nice list by taking major steps on those two big projects. I-19 Ajo

On Friday night at Ajo Way, we’ll be pouring concrete to form the deck on the new bridge that carries Ajo (State Route 86) over Interstate 19. When we begin the work at 10 p.m., we’ll close I-19 in both directions for your safety. Traffic will use the exit and ramps to leave and return to the freeway. Ajo Way will be closed, so there will be no turns at Ajo.

Around sunrise, once the concrete is poured, we’ll open I-19 again but close the exit and entrance ramps. You can use Irvington or 29th Street as alternative exits. By midday on Saturday, Dec. 16, we should be finished and traffic will go back to normal.

Meanwhile in Marana, crews will use Saturday and Sunday to move traffic onto new roads they built during 2017.

On I-10 Saturday night, crews will direct eastbound traffic on I-10 to the new eastbound lanes. Work has already been completed on a bridge that will carry Ina Road over the new freeway lanes. Sometime in January, westbound I-10 will also be moved to the new pavement, giving drivers three lanes in each direction.

There will be no rest on Sunday. About a mile to the west of I-10, we’ll move Ina Road traffic to a new bridge over the Santa Cruz River. Ina Road

After all that holiday fun, we have big plans for celebrating the New Year. On I-10, we’ll demolish the old bridge that once carried westbound traffic, build new westbound lanes, and finish the bridge carrying Ina over the freeway and railroad tracks. On the Santa Cruz River we’ll remove the old bridge and replace it with a new two-lane bridge.

And that’s how we plan to put a bow on two of Pima County’s biggest projects for a year well spent.
Posted by Caroline Carpenter   |  Labels:  Ajo-Way-Interchange, Ina-Road-Interchange, Marana, SR-86, Tucson


Back

The Arizona Ombudsman – Citizens Aide helps you resolve ongoing issues with State Agencies.

Civil RightsTitle VI of the Civil Rights Act of 1964, and the Americans with Disabilities Act (ADA)

Pursuant to Title VI of the Civil Rights Act of 1964, and the Americans with Disabilities Act (ADA), ADOT does not discriminate on the basis of race, color, national origin, age, sex or disability. Persons that require a reasonable accommodation based on language or disability should contact ADOT’s Civil Rights Office at civilrightsoffice@azdot.gov. Requests should be made as early as possible to ensure the State has an opportunity to address the accommodation.

De acuerdo con el título VI de la Ley de Derechos Civiles de 1964 y la Ley de Estadounidenses con Discapacidades (ADA por sus siglas en inglés), el Departamento de Transporte de Arizona (ADOT por sus siglas en inglés) no discrimina por raza, color, nacionalidad, edad, género o discapacidad.  Personas que requieren asistencia (dentro de lo razonable) ya sea por el idioma o por discapacidad deben ponerse en contacto con la Oficina de Derechos Civiles en civilrightsoffice@azdot.gov. Las solicitudes deben hacerse lo más pronto posible para asegurar que el equipo encargado del proyecto tenga la oportunidad de hacer los arreglos necesarios.