The Arizona Department of Transportation will complete a pavement preservation project on US 60 between mileposts 240 and 243.65 (just east of Pinto Valley Mine Road to approximately Reppy Avenue in Miami).

Work is scheduled to begin in mid-summer 2022 and will be completed in several phases:

  • Micromilling of the driving surface
  • Spot repairs to the highway
  • Installation of a chip seal treatment
  • Microseal of the surface
  • Final striping

Project Map

US 60 pavement preservation Project Map

 

The entire project is expected to take about three months, but the most significant traffic restrictions will occur over about six weeks.

Traffic Restrictions

Flaggers and pilot cars will control traffic during working hours. Motorists should expect delays of approximately 15 minutes in each direction. The road will be open to traffic in both directions outside of the scheduled working hours.

In addition, intermittent parking restrictions will be required on the west end of Miami.

Stay Informed

Schedules are subject to change based on weather and other unforeseen factors.  Subscribe to receive project updates and traffic alerts by email. For more information, please call the ADOT Bilingual Project Information Line at 855.712.8530/Teléfono: Línea de Información del Proyecto ADOT: 855.712.8530, or submit a question or comment by email. For real-time highway conditions statewide, visit ADOT's Traveler Information Site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except while driving.