Interstate 8 Pavement Preservation Project between milepost 82 and Gila Bend

The Arizona Department of Transportation, in coordination with the Federal Highway Administration, is repairing the pavement on Interstate 8 near the town of Gila Bend.

The purpose of the project is to extend the life of the pavement and to improve safety and the ride on the existing roadway.

The work consists of removing and replacing the existing pavement. Additional work consists of upgrading existing guardrail, replacing pavement markings and other miscellaneous work.

Project Area

The project is located on I-8 in Maricopa County, approximately 35 miles west of Gila Bend between mileposts 82 and 96.

I-8 Pavement Project area map

What to expect:

The project is scheduled to begin in early 2020 with completion anticipated by mid-March.

Lane restrictions and closures will be necessary. Drivers should plan for possible delays.

Work is scheduled to occur between 6 a.m. and 6 p.m. Mondays  through Thursdays, and from 6 a.m. to 2 p.m. on Fridays.

Stay Informed

Schedules are subject to change based on weather and other unforeseen factors.  Subscribe to receive project updates and traffic alerts by email. For more information, please call the ADOT Bilingual Project Information Line at 855.712.8530 or submit a question or comment by email.  For real-time highway conditions statewide, visit ADOT’s Traveler Information Site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except while driving.