Alert icon

Current and upcoming Loop 101 closures and restrictions (click here)

Learn more

Northbound Loop 101 closed in North Scottsdale May 2-5

Northbound Loop 101 will be closed between Shea Boulevard and Princess Drive/Pima Road from 10 p.m. Friday, May 2, until 5 a.m. Monday, May 5. The northbound Loop 101 on-ramps at 90th Street and Via de Ventura also will be closed. 

  • DETOUR: Drivers may consider using westbound Shea Boulevard to northbound Scottsdale Road to access Loop 101 beyond the closure.

Click here to view a map of this closure and detour.

Show less
Alert icon

Current and upcoming long-term ramp closures

Learn more

Southbound Loop 101 off-ramp at Frank Lloyd Wright Boulevard to be closed for 60 days beginning March 24

The southbound Loop 101 off-ramp at Frank Lloyd Wright Boulevard will be closed beginning at 1 a.m. Monday, March 24, for approximately 60 days

DETOUR: Drivers may consider exiting southbound Loop 101 at Princess Drive/Pima Road and using the southbound Loop 101 frontage road to access Frank Lloyd Wright Boulevard

View a map of the closure and detour.

Show less

Loop 101 (Pima Freeway), Princess Drive/Pima Road to Shea Boulevard Improvements

Loop 101 (Pima Freeway), Princess Drive/Pima Road to Shea Boulevard Improvements

Contents

Overview

The Arizona Department of Transportation, in partnership with the city of Scottsdale, will be widening Loop 101 (Pima Freeway) between Princess Dr/Pima Rd and Shea Blvd by one general-purpose lane in each direction and modifying existing interchanges to improve traffic flow on Loop 101 and the cross streets.

Fact Sheet (English)

Project Elements

  • Widen Loop 101 between Princess Dr/Pima Rd and Shea Blvd by one general-purpose lane in each direction
  • Add a third southbound left turn lane at Princess Dr/Pima Rd interchange
  • Convert Frank Lloyd Wright Blvd interchange to a diamond configuration
  • Add right turn lanes at Raintree Dr and Shea Blvd
  • Update sidewalks to make them ADA compliant
  • Upgrade freeway and ramp lighting
project map
Project area map: (click to enlarge)

 

What to Expect

  • Construction began in January 2024 and will take approximately two years to complete.

  • Work will require lane restrictions and full closures on Loop 101, the interchange ramps and cross streets, and will occur primarily during overnight hours and weekends to minimize traffic impacts. Access to businesses and residences will be maintained.

  • Long-term on- and off-ramp closures will be required (up to 60 days).

  • ADOT will provide advance notice of restrictions and closures to email subscribers and on the project web page.

 

Previous Milestones

 

Stay Informed

..

Please Subscribe to receive project updates and traffic alerts.

  • Phone: ADOT Project Information Line: 855.712.8530
  • Email: [email protected]  
  • Mail: ADOT Communications, 1655 W. Jackson St., MD 126F, Phoenix, AZ 85007

Project Photos

January 2024

Milling of northbound Loop 101 near Princess Drive/Pima Road View 1 Milling of northbound Loop 101 near Princess Drive/Pima Road View 2 Milling of northbound Loop 101 near Princess Drive/Pima Road View 3 Milling of northbound Loop 101 near Princess Drive/Pima Road View 4

Milling of northbound Loop 101 near Princess Drive/Pima Road

June 2024

Workers construction permanent concrete barrier Workers construction a section of concrete barrier Mason working on a concrete barrier segment Masons constructing a section of new concrete barrier New concrete pavement for addition of northbound general purpose lane on Loop 101 New concrete pavement Reinforcing steel rebar for concrete barrier New footings for concrete barrier on Loop 101 Mason working on a section of new concrete pavement on Loop 101 Newly paved concrete pavement on Loop 101 Mason working on a section of new concrete pavement Concrete footing and rebar for concrete barrier
Paving and concrete barrier construction on northbound Loop 101