Interim Improvements: SR 347, I-10 to Northern Maricopa Limits 2023 Road Safety Assessment

Interim Improvements: SR 347, I-10 to Northern Maricopa Limits 2023 Road Safety Assessment

Contents

Background

As the primary route from the city of Maricopa to the Phoenix area, State Route 347 (SR 347) has become a highly traveled corridor. In spring 2023, ADOT completed a safety study on SR 347 between I-10 and the northern city limits of Maricopa. The Road Safety Assessment (RSA) identified potential safety issues related to roadway traffic and evaluated possible ways to improve safety for drivers.

As a result of this assessment, the following are being implemented as interim measures to improve traffic conditions until more long-term improvements can be made.

Project Map

SR347 RSA Final Map

Project Fact Sheet:

STRIPING IMPROVEMENTS

What: Restriping in the following areas to add or extend turn lanes: Queen Creek Road/Interstate 10 interchange; Riggs Road intersection; Casa Blanca Road intersection; Old Maricopa Road intersection; and the Mammoth Way intersection.

Why: Restriping will allow for more vehicles to queue in the turn lanes and potentially alleviate some of the congestion and back-ups at these intersections. 

When: These changes were implemented in October 2023.

Photos of Striping Work at SR 347 intersections:

Casa Grande

Mammoth Way (Cement Plant Access Road)

SR 347 and I-10

Old Maricopa Road

Riggs Road

SIGNAGE AND SIGNAL IMPROVEMENTS

What: New traffic signs added or replaced at intersections. There will also be an additional signal pole installed at the eastbound I-10/Queen Creek off-ramp. Traffic signal timing has been adjusted, and will continue to be monitored and adjusted as needed in the future. Reflective signal head backplates will also be installed.

Why: The new signs and existing sign changes will provide additional guidance for lane usage and improve both driver awareness and line of sight at intersections. The new signal pole (I-10/Queen Creek Road) is an additional signal head that will improve the signal timing and better manage the traffic coming off the freeway. The signal timing adjustments will help alleviate unnecessary stopping of traffic at certain intersections. The reflective backplates on signals improve visibility in both daylight and darkness. 

When: The reflective backplates were installed in October 2023. The new signal pole at the eastbound I-10 ramp at Queen Creek Road was installed in late February 2024.

Emergency Signal Ahead Signs:
The implementation of flashing ‘Signal Ahead’ warning signs and beacons at certain intersections is still under review.  These devices are intended to reinforce awareness of existing traffic signals and can be placed in advance of signalized intersections where the intersection is hidden from the view of approaching travelers. If deemed appropriate, installation will also require environmental clearance.

MEDIAN CROSSOVERS

What: Four existing median crossovers refreshed as needed to allow access for emergency vehicle use. One additional median crossover will be created for an additional access point in the corridor. These locations are: milepost (MP) 177.81, MP 179.22, MP 184.24 and MP 188.62; and a new crossover at MP 185.77.

Why: These improvements will allow for better access for first responders throughout the corridor in the event of an accident. 

When: The work for the median crossovers was completed in January 2024. 

SPEED ADJUSTMENT

What: Removal of signs that currently reduce the speed limit from 65 mph to 55 mph approaching intersections. 

Why: This change is intended to increase compliance, reduce differential speeds, reduce the need for lane changing and potentially reduce rear-end crashes. 

When: New signs were installed in October 2023.

 

Read the full RSA report

Read the Speed Study Summary