New interchange opens on I-10 at Country Club Road in Tucson

Learn more

A new interchange opened at the start of the Monday morning commute, with traffic now flowing on and off Interstate 10 at Country Club Road.

The opening of the interchange is another milestone on the larger $600 million project to reconstruct and widen I-10 from Kino Parkway to Alvernon Way southeast of downtown Tucson.

The interchange is more than just a new connection, as it’s a relatively new kind of interchange for Southern Arizona. This type, a diverging diamond interchange, has one major difference from standard diamond interchanges common around Arizona: Local street traffic makes a temporary shift to the left side while crossing the freeway, allowing for direct left turns onto entrance ramps without waiting at an additional traffic signal.

This is the second diverging diamond in Southern Arizona, following one that opened in Nov. 2021 at I-10 and Houghton Road in east Tucson.

The Country Club Road interchange replaces the former Palo Verde Road interchange, which closed earlier this year. The interchange location was shifted to Country Club Road to allow for safer traffic movement to and from I-10.

Work began in June 2025 with the goal of reducing delays and enhancing safety. Major project features include adding a third lane in each direction of I-10 and building two interchanges.

The project, considered the the largest highway construction project in Southern Arizona history, will include:

  • Widen I-10 to three lanes in each direction between Kino Parkway and Alvernon Way with auxiliary lanes
  • Reconstruct the interchange at Kino Parkway as a diverging diamond interchange
  • Construct a new interchange at Country Club Road that will provide access for traffic that currently uses the interchange at Palo Verde Road to allow for safer traffic movements to and from I-10
  • Remove the existing interchange at Palo Verde Road
  • Construct a new westbound on-ramp at the Alvernon Way interchange
  • Construct an I-10 undercrossing to connect the North and South Kino Sports Complex

Throughout the project, ADOT will maintain two lanes of travel in each direction on I-10 during peak travel times while maintaining access to businesses. Construction is expected to continue through 2028.

The project is the first to result from a study completed in 2020 that recommended how to best improve mobility along a roughly 10-mile stretch of I-10 from I-19 to Kolb Road. The study also identified an alignment for an extension of State Route 210 (Barraza Aviation Parkway) along Alvernon Way that will connect I-10 to downtown Tucson.

Overhead signs for I-10 and Country Club Road above a multi-lane roadway with traffic, construction, and distant mountains.

Show less

Interstate 10: Kino to Country Club Project

Interstate 10: Kino to Country Club Project

Contents

Improving I-10 Kino to Country Club

About This Project

The Arizona Department of Transportation is making improvements to Interstate 10 in Tucson. The Interstate 10: Kino to Country Club project is the first project to come out of the Interstate 10 and State Route 210 Transportation Design Concept Report (DCR) that was completed in 2020.

The I-10: Kino to Country Club project was programmed into the 2024-2028 Five-Year Transportation Facilities Construction Program as a Design/Build in FY 25. The project is currently in construction and scheduled to be completed in summer 2028.

The State Transportation Board has awarded the design-build project to Sundt-Jacobs.

View the I-10/210 Transportation DCR and Final Environmental Assessment (EA) that was completed in 2020.

Fact Sheet

Project Roll Plot

Designs are subject to change

Project Elements

The project will include:

  • Reconstructing I-10 to include three general purpose lanes in each direction between milepost 262 (east of Park Avenue) and Alvernon Way 
  • Reconstructing the traffic interchange at I-10 and Kino Parkway
  • Constructing a new traffic interchange at I-10 and Country Club Road
  • Removing the traffic interchange at Palo Verde Road and I-10
  • Constructing a new I-10 westbound entrance ramp from Alvernon Way
  • Constructing an I-10 undercrossing to connect the North and South Kino Sports Complex

Project Area

I-10 Kino to Country Club Map

Purpose and Need

  • Address traffic congestion
  • Improve safety
  • Increase traffic flow
  • Improve traffic interchanges

Timeline

I-10-Kino to Country Club timeline graphic

Diverging Diamond Interchange (DDI) Resources

The new interchange at Country Club Road and the reconstructed interchange at Kino Parkway will both be Diverging Diamond interchanges (DDI).

What is a Diverging Diamond Interchange (DDI)?

A DDI is a diamond interchange in which both directions of traffic on a cross street briefly switch to the other side of the road to better facilitate traffic flow. Vehicles are guided safely through the interchange using signals, signs and pavement markings.

Like most traffic interchanges, the DDI includes two sets of signals, one on the north side and one on the south side. The crossover points (to transition from the right side to the left side of the road and vice versa) occur at the signals.

Signal operations are simplified in a DDI because there is no need to allocate green light time specifically for left turn movements from the cross street to the on-ramps. Instead, left turns are made using free-flowing lanes after the cross-over.

Is there a DDI in Tucson? Yes, there is a DDI in Tucson at I-10 and Houghton Road. Learn more about Diverging Diamond Interchange.

Close up of DDI Map

Current Construction Phase

Graphic timeline showing four construction phases (2025–2028) for the I-10 and Kino Parkway interchange project, including utility relocations, bridge construction, roadway improvements, traffic switches, and final landscaping.

Stay Informed

...
  • By email: Subscribe to receive project updates and traffic alerts.
  • By phone: Call the ADOT Project Information Line at 855.712.8530.
  • Online: Have a question or comment regarding the project? Email the project team at [email protected].

For real-time highway conditions statewide, follow ADOT on Twitter  (@ArizonaDOT), visit az511.gov or call 511, except while driving