Fortuna Wash bridge to end rain delays on US 95

Fortuna Wash bridge to end rain delays on US 95

September 21, 2016

YUMA – Drivers who have been anticipating a new bridge to carry US 95 traffic over the flood-prone Fortuna Wash don’t have much longer to wait: The bridge is expected to begin taking traffic by the end of November.

The final two concrete pours to complete the deck of the bridge are planned Thursday, Sept. 22, and again on Thursday, Oct. 6, beginning each night about 10 p.m. and continuing until about 6 a.m. the following day. Drivers on US 95 may experience minor delays during those times.

Final work should be completed by spring, but only minor traffic interruptions are expected after the bridge opens to traffic.

US 95 is the only north-south route connecting Yuma with Interstate 10 and Arizona locations along the Colorado River. Until now, it has taken drivers through the wash and has been subject to unexpected closures during heavy rains.

The bridge will make US 95 a safer and more-reliable route for agriculture, international trade and seasonal visitors.

“This bridge is a crucial safety project and will be a huge benefit for the entire region,” said ADOT Southwest District Engineer Paul Patane. “Motorists and commercial vehicles rely on this roadway every day, and with this they can be confident that they won’t be stopped when the wash is flooded.”

The bridge also will make travel more reliable for employees and cargo shipments at Yuma Proving Ground, a U.S. Army facility with more than 3,000 military and civilian employees. The area’s largest employer, it is one of the largest military installations in the world and home to General Motors’ hot-weather vehicle test facility. It has an economic impact of more than $430 million annually.

The Fortuna Wash bridge is designed to accommodate four lanes of traffic but will be initially striped for two lanes with center-turn lane. The $15 million cost is partially funded by a $3.2 million federal grant.