What is the high-level construction schedule for the 32nd Street interchange?

The below activities are subject to change and are weather dependent: April/May 2020 ​Ramp barrier and catch basins Grading and paving 32nd Street southbound: road construction through end of April/early May 32nd Street northbound: road construction in early May to June June/July 2020 ​Cast in place walls Visual wall footings and masonry for ramps Grading and paving Drainage and basin culverts