Long-term ramp closures are needed to realign on- and off-ramps to accommodate the additional general purpose lanes. The following is the current schedule of starting dates for ramp closures through early August. Each closure will last approximately 60 days.

  • April 15, Shea Blvd northbound on-ramp (Reopened Saturday, June 15)
  • April 29, Cactus Rd northbound off-ramp (Currently closed and reopening late June)
  • May 29, Frank Lloyd Wright Boulevard northbound off-ramp (Currently closed and reopening mid July)
  • June 18, Princess Drive/Pima Road northbound on-ramp (Currently closed and reopening Late Aug.)
  • July 8, Frank Lloyd Wright Boulevard northbound on-ramp
  • July 22, Princess Drive/Pima Road northbound off-ramp
  • Aug. 5, Frank Lloyd Wright Boulevard, southbound on-ramp. 

NOTE: This schedule is an approximation and may change. Ramps not listed here will close for reconstruction later.

Map showing locations and schedule for planned long-term on-ramp closures