2019 will be busy year for ADOT in southern Arizona
2019 will be busy year for ADOT in southern Arizona
PHOENIX ‒ Widening the last two stretches of Interstate 10 between Casa Grande and Tucson that remain two lanes in each direction. Opening a modern Ina Road traffic interchange with Interstate 10 in Marana. Launching a major upgrade to State Route 189, the 3.75-mile Nogales highway essential to trade with Mexico.
These are just some of the Arizona Department of Transportation projects finishing or starting in 2019 that are designed to make travel safer and more efficient in southern Arizona.
Four major projects that received a great deal of attention in 2018 are scheduled for completion this year:
- Crews will finish widening 4 miles of I-10 in Casa Grande between Earley Road and Interstate 8. This $43 million project, scheduled for completion by late summer, includes replacing the original bridges over Jimmie Kerr Boulevard to accommodate three lanes in each direction.
- Between Eloy and Picacho, crews are scheduled to complete a $72 million project widening 4 miles of I-10 to three lanes in each direction by creating new travel lanes. The improvements include a new State Route 87 interchange and a first-of-its-kind dust detection zone on 10 miles of I-10 to provide drivers with crucial safety information during dust storms. Completion is scheduled for late summer.
- A $55 million overpass that will carry State Route 347 traffic over the Union Pacific Railroad tracks in Maricopa is scheduled for completion by the end of 2019.
Design work is set to begin by June on the largest project of 2019: a $134 million upgrade of State Route 189, which connects the Mariposa Port of Entry with Interstate 19 in Nogales and carries a large share of produce entering the United States. Planned upgrades include flyover ramps to make a smoother transition between SR 189 and I-19 and a bridge over Frank Reed Road that will improve safety near Nogales High School. The two-year project is expected to be completed in 2021.
In Tucson, construction is scheduled begin this summer on a new interchange at I-10 at Ruthrauff Road. The $101 million, two-year project will be similar to interchange improvements at Ina and Prince roads.
Other major projects expected to begin in 2019 include replacing the 70-year-old Pinto Creek Bridge on US 60 east of Superior and repaving a 7-mile section of State Route 95 north of Parker. Bidding for the Pinto Creek work will take place early this year, while paving on SR 95 began earlier this month and is expected to continue until fall.
For more information on these projects, please visit azdot.gov/projects.