Construction of this segment of SR 30 is planned to occur after the completion of the southward extension of Loop 303 from Van Buren Street to MC 85, which is expected to begin in early 2026. For more information on the Loop 303, Van Buren Street to MC 85 Extension, please visit azdot.gov/L303-MC85-VanBuren.
This area of SR 30 will be designed and constructed in three segments:
- Segment 1: 97th Avenue to Dysart Road
- Segment 2: Dysart Road to Estrella Parkway
- Segment 3: Estrella Parkway to Loop 303
Design for all three segments is expected to be completed in spring 2028 with construction phased from east to west and beginning in fiscal year 2029.