The Arizona Department of Transportation advises drivers of the following closures and restrictions scheduled for work on the US 60 (Grand Avenue) from 85th Avenue to Interstate 17 pavement project. 

The following locations will be CLOSED from 9 p.m. Friday, July 10, to 5 a.m, Monday, July 13, and again from 9 p.m. Friday, July 17, to 5 a.m. Monday, July 20:

  • East- and westbound Camelback Road between 41st Drive and 43rd Avenue
  • North- and southbound 43rd Avenue between Camelback Road and Medlock Drive
  • East- and westbound Grand Avenue will be narrowed to two lanes between Camelback Road and 43rd Avenue
  • The east- and westbound Grand Avenue on- and off-ramps at Camelback Road and 43rd Avenue 
  • Sidewalks will also be closed in the work areas
  • Detours: Drivers may consider using Indian School or McDowell roads as alternate routes for east- and westbound travel and 35th or 51st avenues as alternate routes for north- and southbound travel.   

Ongoing restrictions through July 28:

  • Westbound Grand Avenue will be narrowed to two lanes from Royal Palm Road to 71st Avenue
Show less

US 60 (Grand Avenue), 85th Avenue to I-17 Pavement Project

US 60 (Grand Avenue), 85th Avenue to I-17 Pavement Project

Contents

Overview

The Arizona Department of Transportation will be conducting a pavement rehabilitation project along an 11-mile section of US 60 (Grand Avenue) from 85th Avenue to Interstate-17. The project will replace the worn pavement to improve the driving experience and safety.

Project Area

US 60 (Grand Avenue), 85th Avenue to I-17 Pavement Project Map

The project area extends along US 60 (Grand Avenue) between 85th Avenue and I-17.

Project Elements

  • Removing and replacing the existing asphalt pavement
  • Replacing lane striping and other pavement markings
  • Modifying the existing sidewalk curb ramps as needed to comply with Americans with Disability Act standards

Project Schedule

Construction is anticipated to begin in early May 2026 and take approximately nine months to complete. The schedule is subject to change based on weather or other unforeseen factors.

What to Expect

  • The project will require overnight lane restrictions on Grand Avenue and cross streets.
  • Access to property will be maintained.
  • The pavement removal will generate some noise and dust; the contractor will be required to follow Maricopa County dust control requirements.
  • ADOT will provide advance notice of restrictions and closures to email subscribers and on the project website.

Subscribe to receive project updates and traffic alerts by email.

Questions

ADOT welcomes your questions. Please contact us in any of the following ways:

  • Phone: 855.712.8530
  • Email: [email protected]
  • Mail: 1655 W. Jackson St, Room 179, MD 126F, Phoenix, AZ 85007