Alert icon

Current and upcoming closures and restrictions for US 60/Loop 303 Interchange Improvements (click here)

Learn more

There are no more anticipated restrictions/closures needed for 2024. The project will resume late March 2025.

Slow down, stay alert and be prepared to merge with caution when approaching and traveling through all work zones.

Show less

US 60/Loop 303 Traffic Interchange Improvements

US 60/Loop 303 Traffic Interchange Improvements

Contents

Overview

The Arizona Department of Transportation completed a feasibility study in 2022 to assess the US 60 and Loop 303 (Estrella Freeway) interchange and other intersections along US 60 from 163rd Avenue in Surprise to R H Johnson Boulevard in Sun City West.  

The study evaluated several near-term and long-term projects to improve traffic flow and developed conceptual design plans and cost estimates for each improvement.

Near-term improvements refer to smaller projects that would mitigate some traffic congestion and could be implemented sooner than the long-term improvements.

Project Area Map

US 60 - Loop 303 Traffic Interchange Improvements map

US 60/Loop 303 and US 60/163rd Avenue Additional Near-Term Improvements 

In October 2024, the Maricopa Association of Governments approved new funding to implement additional US 60 (Grand Avenue)/Loop 303 and US 60/163rd Avenue near-term improvements. ADOT is currently designing these improvements with construction anticipated to begin in summer 2025 and take approximately six months to complete.

These improvements include:

US 60/Loop 303

  • Add a second right turn lane on eastbound US 60 to southbound Loop 303
  • Add a third left turn lane from southbound Loop 303 to westbound US 60
  • Lengthen the two-lane portion of southbound Loop 303 on-ramp

US 60/163rd Avenue

  • Add a dedicated eastbound right turn lane into the drive between Deer Valley Road and 163rd Avenue and an acceleration lane along US eastbound 60
  • Add a fourth lane in each direction along US 60 through the 163rd Avenue intersection

What to Expect

  • Construction is anticipated to begin in summer 2025 and take approximately six months to complete.
  • Work will require lane restrictions and ramp closures and is expected to occur primarily during overnight hours and weekends to minimize traffic impacts.
  • ADOT will provide advance notice of restrictions and closures to email subscribers and on the project web page.

 

Short-Term Improvements

In April 2023 the Arizona State Legislature approved funding to initiate final design and construction of some short-term improvements. Some of these improvements were made in December 2023. Construction of the remaining improvements began summer 2024 and were substantially completed in late-November 2024.

These improvements include:

US 60/163rd Avenue

  • Add a third left turn lane from southbound 163rd Avenue to US 60
  • Add a second right turn lane from northbound/westbound US 60 to 163rd Avenue. (December 2023)
  • Extend the existing east- and westbound US 60 third lane to 163rd Avenue (westbound December 2023; eastbound summer 2024)

Note: No pavement widening is needed for any of these improvements.

US 60/163rd Avenue

 

US 60/Loop 303

  • Add a second lane to the northbound Loop 303 off-ramp at US 60
  • Widen the Loop 303/US 60 intersection and Loop 303 northbound off-ramp to provide three dedicated left turn lanes and one dedicated right turn lane from the northbound Loop 303 off-ramp to US 60

US 60/Loop 303

 

Other improvements include restriping, new signs, traffic-signal timing adjustments and railroad coordination.

Long-Term Improvements

The feasibility study identified some possible long-term improvements that could be implemented as part of future reconstruction of the US 60/Loop 303 interchange.

Possible improvements include:

  • Construct a diamond interchange at US 60 and Loop 303
  • Construct new southbound Loop 303 off-ramp and northbound Loop 303 on-ramp over the railroad tracks
  • Grade separate eastbound US 60 through lanes between 163rd Avenue and RH Johnson Boulevard to go over Loop 303.
  • Build a US 60 overpass at 163rd Avenue. Traffic on 163rd Avenue could be serviced by a ground-level Single Point Urban Interchange (SPUI) interchange.

NOTE: These improvements are subject to change. Further study will be required to determine the final configuration of the long-term improvements.

Schedule

  • In June 2022 the US60/SR303L Traffic Interchange (TI) Feasibility Report (See report under the Document tab) was completed.
  • In December 2023 ADOT completed the following short-term improvements:
    • Added a second right turn lane from northbound/westbound US 60 to 163rd Avenue.
    • Extended the existing westbound US 60 third lane to 163rd Avenue
    • Restriped westbound US 60 for third lane and two right-turn lanes to 163rd Avenue
  • Construction for the other short-term improvements began in late-July 2024 and was substantially completed in late-November 2024. 

Documents

 

Stay Informed

...

Please Subscribe to receive project updates and traffic alerts.

  • Phone: ADOT Project Information Line: 855.712.8530
  • Email: [email protected]
  • Mail: ADOT Communications, 1655 W. Jackson St., MD 126F, Phoenix, AZ 85007