I-19 Frontage Roads Expansion Project between Ruby Road and Rio Rico Drive

I-19 Frontage Roads Expansion Project between Ruby Road and Rio Rico Drive

Contents

Overview

Santa Cruz County, in partnership with the Arizona Department of Transportation, is in the design phase for a local project to make overall improvements to Interstate 19 frontage roads between Ruby Road and Rio Rico Drive. The project, located in Rio Rico, will start by making improvements to traffic flow in the area near Rio Rico Drive, with further improvements happening at Ruby Road at a later date. This project will provide better access to businesses, residences, Calabasas School, and emergency services along the corridor.

Planned Improvements

  • Extending the two-way westbound frontage road from Calle Calabasas north to Rio Rico Drive via Camino Caralampi
  • Widening and converting the eastbound frontage road to a two-way road from Kipper Street north to Rio Rico Drive
  • Constructing a new slip ramp for the eastbound frontage road traffic at Rio Rico Drive to northbound I-19
  • Installing lighting, signage, slip ramps and pavement marking along the east- and westbound frontage roads
  • Installing traffic signals, pavement marking and signage on Camino Caralampi, Yavapai Drive and Rio Rico Drive
  • Improving drainage infrastructure by modifying or installing box culverts, pipes, headwalls, scuppers, channels and retention basins within the project area
  • Removing and replacing fencing, as necessary
  • Removing and replacing cattle guards, as necessary
  • Relocating utilities, as necessary
  • Installing landscaping and erosion control devices

Project Area Map

I-19 Frontage Road Expansion Project between Ruby Road and Rio Rico Drive

Project Schedule

  • The project is currently in the design phase.
  • Design is expected to be completed in spring 2027.
  • Construction on the east frontage road improvements is anticipated to start summer 2027.

Schedules are subject to change due to weather and other unforeseen circumstances.

Open House Details

Project information boards will be on display for viewing and the project team will be on hand to discuss the project.

Date: Tuesday, Sep. 22, 2026, 5 p.m. - 7 p.m.

Locations:
Gabilondo-Zehentner Centennial County Service Center
275 Rio Rico Drive
Rio Rico, AZ 85648

Comments/Questions: Project comments can be provided through Oct. 6, 2026, in the following ways:

Stay Informed

...
  • Contact: Santa Cruz County Project Manager J. Leonard Fontes Jr. or HDR Project Manager Ted Smithwick, PE
  • Phone: 520.375.7830 or 602.522.4336
  • Email: [email protected] or [email protected]
  • Mail: HDR Engineering Inc., 1 South Church Ave., Suite 1400, Tucson, AZ 85701