Improving I-17

Cue the fireworks, then enjoy this video of blasting work along I-17

Cue the fireworks, then enjoy this video of blasting work along I-17

SR24-1

Cue the fireworks, then enjoy this video of blasting work along I-17

Cue the fireworks, then enjoy this video of blasting work along I-17

By Laura Douglas / ADOT Communications
July 3, 2023
Graphic saying that 120,000 cubic yards if rocks were blasted at the I-17 Anthem Way to Sunset Poit project and that equals 6,000 dump trucks. Which, lined up, would be equal to the entire length of the 23-mile project.

It may not be a dazzling Fourth of July fireworks show, but controlled rock blasting for the I-17 Improvement Project is a pretty spectacular sight in our eyes. And it’s a necessary operation to make way for the additional lanes between Anthem Way and Sunset Point.

The project recently hit a major milestone when controlled rock blasting was completed in the northern segment between Coldwater Road and Sunset Point. The work included 42 blasts, which took place over six months, in order to loosen rocks to make way for the construction of the new 8 miles of flex lanes in this area.

Rocks that are removed during blasting are crushed and turned into aggregate base, a material that will be used in the paving process for both the new general purpose lanes and flex lanes that are being built along the 23-mile project corridor.

A major component of the I-17 Improvement Project process, controlled rock blasting is a technique used to loosen the rock, where construction requires large amounts of material to be moved to accommodate widening. Crews moved approximately 120,000 cubic yards of blasted rock from the northern segment, roughly equal to more than 6,000 truckloads.

Blasting will occur throughout three sections of the project corridor, with about a third of the blasting for the project now completed. Controlled rock blasting has now begun in the next section between Table Mesa Road and Black Canyon City.

Full closures of I-17 in both directions are necessary near the blast area when controlled rock blasting occurs, generally between 10 and 11 p.m. two to three times a week. Blasting is only scheduled for weeknights and drivers should expect delays of at least one hour and backups of about 2 miles when controlled rock blasting is scheduled.

Additional details about the I-17 Improvement Project, which is expected to be completed in 2025, can be found at ImprovingI17.com.

Heavy Lifting: First girders installed on I-17 Improvement Project

Heavy Lifting: First girders installed on I-17 Improvement Project

I-17 101 traffic interchange

Heavy Lifting: First girders installed on I-17 Improvement Project

Heavy Lifting: First girders installed on I-17 Improvement Project

April 3, 2023

New River Road traffic interchange first to mark girder milestone

PHOENIX – Drivers who travel Interstate 17 between Anthem Way and Sunset Point will undoubtedly notice a very different scene, as construction along this 23 miles of scenic highway is well underway.

Before the road is widened and the flex lanes are added, there is significant bridge work that must take place. The New River Road traffic interchange at milepost 232 has been under construction, as the bridges on both the northbound and southbound sides need to be widened from two lanes in each direction to three lanes. Massive girders were recently installed on both bridges in order to support the bridge decks, or the actual roadway, that vehicles will travel over once the project is complete.

The girders were set during the overnight hours, which is when most of the work is completed for the Arizona Department of Transportation’s I-17 Improvement Project. Crews from the Kiewit-Fann Joint Venture developer team set nine girders on each bridge during a two-night operation. There are three sizes of girders, or beams, with the largest weighing about 45,000 pounds (22.5 tons) and the smallest weighing about 30,000 pounds (15 tons).

Setting the girders is a critical operation for the construction crews and one that requires several hours of careful work. Getting the girders hoisted up and then set into place requires significant coordination, safety precautions and quality control. Girder placement signifies the start of completing the bridges at the New River Road traffic interchange, which is a major milestone.

The New River Road traffic interchange bridges are the first two of 10 bridges that will be widened as part of the I-17 Improvement Project. These two bridges are expected to be fully completed by late summer. Three additional bridges are being fully constructed or replaced as part of this project.

More about the I-17 Improvement Project:

Once complete in 2025, the I-17 Improvement Project will help alleviate congestion and improve safety and traffic flow north of the metro Phoenix region. The 23 miles of improvements include 15 miles of roadway widening from Anthem Way to Black Canyon City. One travel lane will be added in each direction along this stretch. In addition, an eight-mile flex lane system will be constructed from Black Canyon City to Sunset Point. Flex lanes are a new feature for Arizona’s highway system and are proven technology to help reduce congestion on I-17 during peak travel times and allow for traffic movement during emergency situations.

The I-17 flex lanes will operate as a separate, two-lane roadway carrying one direction of traffic at a time depending on the greatest need along the steep, winding eight miles between Black Canyon City and Sunset Point. For example, the flex lanes will be able to carry heavy northbound traffic on a Friday or heavy southbound traffic on a Sunday. Similarly, ADOT will be able to open the flex lanes to accommodate traffic any time if a crash or other incident causes long delays.

The two flex lanes will be next to, but physically separated from southbound I-17 using concrete barriers. Access to the flex-lane entrances will be controlled by gates. Overhead message signs will alert drivers to the open direction of the flex lanes. The flex lanes will be operational seven days a week.

For more information about the I-17 Improvement Project, visit improvingi17.com, call 877.476.1717 or email [email protected].

Click on images to view enlarged.

New River -I-17 Bridge

New River project photos

New River project photos

New River project photos