kingman

Contract awarded for I-40/US 93 interchange project in Kingman

Contract awarded for I-40/US 93 interchange project in Kingman

I-17 101 traffic interchange

Contract awarded for I-40/US 93 interchange project in Kingman

Contract awarded for I-40/US 93 interchange project in Kingman

March 15, 2024

Construction starts this summer on free-flowing connection

KINGMAN – The State Transportation Board has awarded a $106 million construction project to build a free-flowing traffic interchange for Interstate 40 and US 93 in Kingman.

With the contract awarded to Fisher Sand & Gravel Co. during the board’s meeting on Friday, March 15, construction is expected to begin this summer and take two and a half years.

The interchange in west Kingman is designed to reduce congestion on the highly traveled route between Phoenix and Las Vegas while improving safety, travel times and reliability. While vehicles now must stop at a traffic signal where Beale Street intersects with I-40, the system-to-system interchange will feature ramps that allow traffic to flow freely.

The interchange is designed to handle projected traffic growth for the next 25 years. 

For more information, please visit azdot.gov/WestKingmanTI.

Public meetings slated for Kingman and Flagstaff to present Electric Vehicle charger plan

Public meetings slated for Kingman and Flagstaff to present Electric Vehicle charger plan

I-17 101 traffic interchange

Public meetings slated for Kingman and Flagstaff to present Electric Vehicle charger plan

Public meetings slated for Kingman and Flagstaff to present Electric Vehicle charger plan

October 27, 2022

Two public meetings in northern Arizona have been scheduled by the Arizona Department of Transportation to share the details of its plan to develop a network of electric vehicle fast charging stations along interstate highways in Arizona.

The first meeting is in Kingman and will be held on Tuesday, November 1st from 5-7 p.m. at the Mohave County Administration Building, 700 W Beale Street.

In Flagstaff, the meeting is scheduled for Wednesday, November 2nd from 5-7 p.m. at the Flagstaff Aquaplex, 1702 N Fourth Street.

This is an open house format without a formal discussion; a recorded presentation with study details will be shown throughout the meeting and study team members will be on hand to provide information and answer questions. 

Under the recently-approved plan funded through the federal National Electric Vehicle Infrastructure (NEVI) Program, Arizona’s Interstate highways including I-40, I-17 and I-15 in northern Arizona, will have improved or new charging stations placed in locations along the highway no more than 50 miles apart. That work is slated to begin in 2023. 

The goal of the federal NEVI program is to encourage adoption of electric vehicles by improving the accessibility, reliability and equity of clean transportation options.

For more information about the EV plan, additional ways to provide input including an online survey, as well as details on upcoming meetings throughout the state, visit /planning/transportation-studies/arizona-electric-vehicle-program

 

ADOT seeking federal grant for the West Kingman Traffic Interchange

ADOT seeking federal grant for the West Kingman Traffic Interchange

I-17 101 traffic interchange

ADOT seeking federal grant for the West Kingman Traffic Interchange

ADOT seeking federal grant for the West Kingman Traffic Interchange

August 16, 2022

KINGMAN – The Arizona Department of Transportation has submitted an application for a federal bridge grant that, if awarded, would allocate nearly $73 million toward the construction of the planned West Kingman Traffic Interchange that will provide a free-flowing connection between US 93 and Interstate 40.

If the grant is awarded, those funds would be added to state-matching funds and other federal funds to cover the estimated $160.7 million cost of construction. The grant is funded under the U.S. Department of Transportation’s Bridge Investment Program and would cover the bridge improvement portion of the new interchange.

The West Kingman Traffic Interchange, planned for construction in 2024, is a critical component of the highly traveled route between Phoenix and Las Vegas. The I-40 and US 93 area has regional and national economic significance due to the amount of goods that pass through the area.

The traffic interchange will improve safety, reduce travel times, and improve reliability for people and freight moving between the fast-growing metropolitan areas of Phoenix and Las Vegas by establishing a seamless freeway connection.

US 93 between Wickenburg and Kingman is designated as the future Interstate 11. The West Kingman Traffic Interchange will play a critical role in laying the foundation for this future interstate that would connect Phoenix and Las Vegas. With the grant, ADOT will be able to move funds to address other transportation needs while ensuring the construction of the much-needed West Kingman Traffic Interchange goes forward as planned.

For more information, visit azdot.gov and transportation.gov.

ADOT to compete for federal grant to speed up US 93 improvements

ADOT to compete for federal grant to speed up US 93 improvements

I-17 101 traffic interchange

ADOT to compete for federal grant to speed up US 93 improvements

ADOT to compete for federal grant to speed up US 93 improvements

May 25, 2022

The Arizona Department of Transportation submitted a competitive grant bid that, if awarded, would allocate approximately $65 million to speed up already-planned improvement projects on US 93 between Wickenburg and Interstate 40. 

If the grant application is approved, these competitive funds would be added to state match funding and additional federal dollars, for a potential total of more than $200 million for the improvements on US 93, in partnership with the Federal Highway Administration. 

The prospective funding and work would come from an Infrastructure for Rebuilding America (INFRA) grant through the federal Infrastructure Investment and Jobs Act (IIJA). It would complement work already completed by ADOT, improving safety and removing existing bottlenecks along a major route between Phoenix and Las Vegas. 

The projects include a three-mile stretch of the highway near Cane Springs, four and a half miles near Big Jim Wash and three miles near Vista Royale. Together, these three projects will widen more than 10 miles of US 93 to a four-lane divided highway. Currently, fewer than 40 miles of US 93 between Wickenburg and I-40 remain a two-lane highway.

ADOT has dedicated nearly half a billion dollars to widening and improving US 93 in this region over the last several years. ADOT's long-term vision is to transform this highly traveled route into a four-lane divided highway. 

Improvements to these three segments will enhance safety and further prepare Arizona and the region for increased population growth, as well as economic and freight activity. US 93 between Wickenburg and Kingman is designated as the Future Interstate 11. With the grant, ADOT will improve project delivery through accelerated construction techniques delivering the improvements earlier than traditionally available.

For more information:/ and https://www.transportation.gov/

 

Adopt a Highway: Volunteers collect tons of trash from Arizona highways

Adopt a Highway: Volunteers collect tons of trash from Arizona highways

I-17 101 traffic interchange

Adopt a Highway: Volunteers collect tons of trash from Arizona highways

Adopt a Highway: Volunteers collect tons of trash from Arizona highways

September 23, 2021

Arizona Department of Transportation volunteers answered the call to participate on National CleanUp Day, Sept. 18, by removing more than 150 bags, or 2,053 pounds of trash from alongside Arizona’s highways. 

Forty groups from all corners of the state: Page, Yuma, Concho, Vernon, Show Low, Prescott, Chino Valley, Congress, Kingman, Lake Havasu City, Tucson, Bouse, Claypool, Sahuarita and Bullhead City, registered with ADOT for the event on the Adopt a Highway website. 

Adopt a Highway Program Manager Mary Currie said, “It’s a win for communities and the state of Arizona. One-day permits offer volunteers a way to explore one type of volunteer work among many, and to be a part of the litter solution. They get first hand experience on the process for adopting and how to conduct a litter cleanup safely. Our experience has been that some of these groups decide to complete the adoption for two-years and become regular caregivers of their segment”. 

More than half of the groups registering for the cleanup were new volunteers interested in participating for one day rather than a two-year adoption.

Every day Adopt a Highway program volunteers are giving back to Arizona somewhere in the state. ADOT strives to make it safe and as easy as possible for them to continue volunteering.  

These individual volunteers made a positive impact for drivers on the state highway system by removing all types of litter, including: cigarette butts, plastic bags and bottles, aluminum cans, and other unsightly trash. Car bumpers and refrigerator doors were also found along the way. A very dangerous type of trash for travelers.

Michele Michelson and her group of eight volunteers opted for a one-day permit to help clean up SR 89A in Prescott Valley. “We are all very proud to be here in this beautiful sunshine to keep the county, the town and our state clean. I saw ADOT’s post on facebook and registered. Here we are and we’ll do it again. Who doesn’t want to keep their community clean. Thank you ADOT for offering this opportunity.”

In return for a two-year permit and a sign recognizing their group’s segment, Adopt a Highway volunteers agree to:

Adopt a minimum of two miles of state highway

Always wear Federal Highway Administration required ANSI Class II Safety vests

Read a safety brief and watch a safety video before each cleanup

Contact ADOT before cleaning up their sections

File an activity report after each cleanup, telling ADOT how many bags of litter was collected

Clean their sections at least once and preferably three or more times per year

Motorists can support Adopt a Highway volunteers by slowing down where people are picking up litter and always driving with extra caution and care. 

To learn more about ADOT’s Adopt a Highway volunteer program, please visit azdot.gov/adoptahighway.