RT BMP/ LOCAL ENTITY CO TRACS LOCATION DISTRICT TYPE of WORK ALTERNATIVE DELIVERY DB/CMAR TYPE OF FUNDS COST ($000) FY QTR
   77  PN 102.5 H8267 POWER LINE - SAN MANUEL ROAD SouthCentral CONSTRUCT SAFETY IMPROVEMENTS   HSIP $1,074 9/30/2019
   60  MA 153.4 F0141 BETHANY HOME ROAD & NORTHERN AVE Central LEFT TURN BAY EXTENSION & RR  SAFETY IMPROVEMENTS   NHPP $1,356 9/19/2019
   70  GI 261.0 F0149 RAMBOZ WASH - MP 262 SouthEast EXTEND EB PASSING LANE   STBG $3,200 8/23/2019
   82  SC  19.3 F0128 SONOITA CREEK BRIDGE SouthCentral CONSTRUCT SCOUR RETROFIT   STBG $265 8/23/2019
   82  SC  23.8 F0140 CASA BLANCA WASH BRIDGE SouthCentral CONSTRUCT SCOUR RETROFIT   STBG $240 8/23/2019
  177  PN 152.3 F0129 MINERAL CREEK BRIDGE SouthEast BRIDGE SCOUR RETROFIT AND DECK REHABILITATION   STBG $1,800 9/13/2019
  180  NA 325.5 H8939 JIM CAMP WASH BRIDGE & COTTONWOOD WASH BRIDGE NorthEast DECK REHABILITATION   STBG $3,600 8/30/2019
  264  NA 362.7 H8943 DINNEBITO WASH BRIDGE NorthEast DECK REHABILITATION   STBG $1,900 9/12/2019
   10  PN 176.0 F0113 SR 587 - SR 387 SouthCentral PAVEMENT REHABILITATION   NHPP $22,000 12/11/2019
   10  PM 262.4 F0173 AJO WAY,COUNTRY CLUB,IRVINGTON,PALO VERDE STRS SouthCentral CONSTRUCT BRIDGE REHABILITATION   NHPP $1,200 11/26/2019
   40  CN 190.4 F0151 RIORDAN ATSFRR OP EB/WB NorthCentral CONSTRUCT SCOUR RETROFIT   NHPP $300 11/18/2019
   40  CN 191.0 H8777 W FLAGSTAFF TI OVERPASS EB/WB NorthCentral CONSTRUCT BRIDGE REPLACEMENT   NHPP $9,350 11/15/2019
   40  CN 198.1 H8815 BUTLER AVE TI OP & 4TH ST UP NorthCentral BRIDGE REPLACEMENT   NHPP $14,000 11/5/2019
   40  CN 211.0 F0108 WINONA TI UNDERPASS NorthCentral CONSTRUCT BRIDGE REHABILITATION   NHPP $5,300 12/20/2019
   40  CN 224.7 H8928 BABBITTS TANK WB & BUFFALO RANGE TI OP EB/WB NorthCentral CONSTRUCT BRIDGE  REHABILITATION   NHPP $3,250 12/23/2019
   40  CN 230.0 F0152 TWO GUNS TI UP  & METEOR CRATER TI UP NorthCentral REPLACE BRIDGE DECK   NHPP $4,000 12/24/2019
   40  AP 347.0 F0088 BLACK CREEK EB/ WB  & HOUCK TI UP NorthEast CONSTRUCT BRIDGE REHABLILITATION   NHPP $5,800 11/5/2019
   64  CN 205.0 F0089 PIPELINE RD - AIR PARK NorthCentral PAVEMENT REHABILITATION   NHPP $7,500 12/18/2019
   17  MA 196.6 F0115 CENTRAL AVENUE BRIDGE Central CONSTRUCTION   RARF $20,440 11/27/2019
   60  GI 298.3 F0156 SALT RIVER CANYON - CIBECUE SouthEast FENCE REPLACEMENT   STBG $1,100 12/24/2019
   73  GI 324.0 F0117 W OF RIM TANK - W OF CANYON DAY NorthEast PAVEMENT REHABILITATION   STBG $3,600 12/20/2019
   73  NA 348.0 F0109 POST OFFICE CANYON BRIDGE NorthEast CONSTRUCT BRIDGE REHABILITATION   STBG $2,500 12/3/2019
   89A CN 387.0 H8778 PUMPHOUSE WASH BRIDGE NorthCentral CONSTRUCT BRIDGE REHABILITATION   STBG $3,500 10/22/2019
   89A CN 388.0 H8907 OAK CREEK CANYON NorthCentral DRAINAGE AND SEDIMENT CONTROL   STP  $2,300 10/22/2019
 0000  SC SSC SS998 RIO RICO DR & PENDLETON DR INTERSECTION SouthCentral INTERSECTION IMPROVEMENTS   HSIP $1,035 9/23/2019
 0000  MA AVN SL738 VAN BUREN ST; AF RIVER - 113TH AVE, AVONDALE Central CONSTRUCT MULTI USE PATH   STB  $2,489 9/19/2019
0 MO MMO T0095 PIERCE FERRY RD. - LLOYD ST. TO 13TH ST. NorthWest ROADWAY WIDENING & INTERSECTION IMPROVEMENTS     $1,800 11/25/2019
 0000  PN CLG T0169 MACRAE RD AND WOODRUFF RD SouthCentral RUMBLE STRIPS   HSIP $248 11/5/2019
   19  SC   8.0 F0101 RUBY RD TI UP SouthCentral REPLACE DECK   NHPP $2,200 12/9/2019
    8  MA  82.0 F0094 EAST OF YUMA / MARICOPA COUNTY LINE SouthWest PAVEMENT REHABILITATION   NHPP $26,000 9/16/2019
 0000  GI GGI T0087 COLCORD RD BR 11465 - .8M WEST OF CHAMBERLIN TRAIL SouthEast CONSTRUCT BRIDGE     $1,170 12/20/2019
 0000  CH SVS T0183 ADAPTIVE SIGNAL CONTROL - PHASE 1 SouthCentral INSTALL ADAPTIVE SIGNAL CONTROLS   HSIP $911 1/10/2020
 0000  PN ELY T0168 JIMMIE KERR BLVD: CASA GRANDE AVE - MILLIGAN RD SouthCentral SAFETY IMPROVEMENTS     $296 JANUARY
   86  PM  88.2 F0159 MP 88.25 - QUIJOTOA SouthCentral REPLACE GUARDRAIL   STBG $900 JANUARY
   89  YV 295.0 F0275 WALDEN BLVD - PONDEROSA PARK ROAD NorthWest CHIP SEAL   STBG $1,400 JANUARY
  180  CN 215.0 F0060 SR 40B - ASPEN AVENUE NorthCentral CONSTRUCT TURN LANE   STBG $1,340 JANUARY
   10  LA  52.0 F0199 BOUSE WASH REST AREA SouthWest REHABILITATE REST AREA   NHPP $5,300 JANUARY
   69  YV 279.1 F0274 MAIN STREET - PRESCOTT LAKE PARKWAY NorthWest ASPHALT SPOT REPAIR   NHPP $2,800 JANUARY
   70  GH 293.4 H8888 BYLAS - PIMA SouthEast MINOR PAVEMENT PRESERVATION   STBG $3,050 JANUARY
   69  YV 279.1 F0274 MAIN STREET - PRESCOTT LAKE PARKWAY NorthWest ASPHALT SPOT REPAIR   NHPP $2,800 JANUARY
   10  PM 274.8 H8887 HOUGHTON ROAD TI SouthCentral CONSTRUCT TRAFFIC INTERCHANGE   NHPP $39,359 FEBRUARY
  303L MA 125.2 F0116 HAPPY VALLEY PARKWAY - LAKE PLEASANT PARKWAY Central CONSTRUCT GENERAL PURPOSE LANE    RARF $36,200 FEBRUARY
   19  PM  46.0 F0138 HELMET PEAK TI UP SouthCentral CONSTRUCT BRIDGE REHABILITATION   NHPP $3,100 FEBRUARY
  999  SW   0.0 F0213 HORIZONTAL CURVE WARNING SIGNS, PHASE III NorthCentral CONSTRUCT HORIZONTAL CURVE WARNING SIGNS   HSIP $800 FEBRUARY
   19  PM  42.8 F0174 DUVAL MINE RD TI - PIMA MINE RD TI SouthCentral PAVEMENT REHABILITATION   NHPP $18,000 FEBRUARY
  999  SW   0.0 F0214 HORIZONTAL CURVE WARNING SIGNS PHASE IV NorthCentral CONSTRUCT HORIZONTAL CURVE WARNING SIGNS   HSIP $508 FEBRUARY
  180  CN 235.2 F0044 NF 151 - NF 223J NorthCentral MINOR PAVEMENT PRESERVATION   FA   $4,610 FEBRUARY
   77  PN  94.7 F0034 WILLOW SPRINGS RD - OLD HWY 77 SouthCentral MNOR PAVEMENT PRESERVATION   STBG $2,800 FEBRUARY
   68  MO   8.5 F0164 OLD KINGMAN HIGHWAY - UNION PASS NorthWest CONSTRUCT SAFETY IMPROVEMENTS   HSIP $5,900 MARCH
   40B CN 195.6 H8905 RIO DE FLAG BRIDGE NorthCentral CONSTRUCT BRIDGE REPLACEMENT   NHPP $5,600 MARCH
  260  AP 394.0 H8269 LITTLE COLORADO RIVER BRIDGE NorthEast CONSTRUCT SCOUR RETROFIT AND BRIDGE REPAIR   STBG $700 MARCH
 0000  MO LHV T0202 ACOMA BLVD N AND PIMA DRIVE NORTH NorthWest PEDESTRIAN HYBRID BEACON   HSIP $460 MARCH
   89A CN 375.1 F0154 MP 375.1 & MP 389.2 SEDONA NorthCentral ROCKFALL MITIGATION   STBG $3,362 APRIL
  160  CN 322.0 F0243 WARRIOR DRIVE  - MP 324.5, TUBA CITY NorthCentral INSTALL LIGHTING   HSIP $696 APRIL
 0000  LA   0.0 T0167 FARMERS BRIDGE SouthWest BRIDGE REHABILITATION     $198 APRIL 
 0000  PN CSG T0180 PEART RD; JIMMIE KERR BLVD - AVENIDA ELLENA SouthCentral LEFT TURN LANE, RUMBLE STRIPS & LIGHTING   HSIP $616 APRIL
   95  YU  80.0 F0289 MP 80 - CRYSTAL HILL ROAD SouthWest CHIP SEAL   FA   1950 MAY
   93  MO  48.0 H8659 WINDY POINT ROAD - MINERAL PARK ROAD NorthWest SHOULDER  WIDENING   HSIP $7,500 MAY
   95  MO 238.5 F0146 AZTEC ROAD - S. BULLHEAD CITY PARKWAY NorthWest RAISED MEDIAN   HSIP $1,239 MAY
   95  MO 249.0 F0209 7TH STREET - AVIATION WAY NorthWest RAISED MEDIAN & PEDESTRIAN IMPROVEMENTS   HSIP $696 MAY
    8  YU  37.1 F0092 AVENUE 36E - MP 46 SouthWest PAVEMENT REHABILITATION   NHPP $17,500 MAY
   10  LA  18.1 H8630 TYSON WASH BRIDGE EB/WB & QUARTZSITE PED SouthWest CONSTRUCT BRIDGE REHABILITATION   NHPP $2,000 MAY
   24  MA   1.0 H8915 ELLSWORTH RD - IRONWOOD DR Central CONSTRUCT NEW ROADWAY   NHPP $15,091 MAY
   40  MO  23.0 F0162 I-40 BRIDGES,MACKENZIE WASH EB - GRIFFITH WASH WB NorthWest CONSTRUCT BRIDGE  REHABILITATION   NHPP $7,000 MAY
 0000  PM ITO T0223 IR34 & IR42, TOHONO O'ODHAM NATION SouthWest SAFETY IMPROVEMENTS   HSIP $952 MAY
 0000  MO MMO T0175 COURTWRIGHT AND PIERCE FERRY RD NorthWest RUMBLE STRIPS   HSIP $547 MAY
   10  MA 112.3 F0119 SR85 - VERRADO WAY Central CONSTRUCT GENERAL PURPOSE LANE   NFP  91700 JUNE
  347  MA 188.0 F0208 SR 347 & OLD MARICOPA ROAD INTERSECTION Central INSTALL TRAFFIC SIGNAL   HSIP $350 JUNE
69 YV 265.0 F0269 SR-69 AND SPRING LANE INTERSECTION NorthWest INSTALL TRAFFIC SIGNAL   HSIP 700 JUNE
69 YV 265.0 F0269 SR-69 AND SPRING LANE INTERSECTION NorthWest INSTALL TRAFFIC SIGNAL   HSIP 700 JUNE
   77  PM  68.1 F0248 JCT I-10 - RIVER SouthCentral PAVEMENT REHABILITATION   NHPP $12,515 JUNE
   77  PM  72.1 H8919 RIVER RD - CALLE CONCORDIA SouthCentral RECONSTRUCT ROADWAY & LIGHTING   NHPP $26,410 JUNE
   89  CN 544.0 F0237 HORSESHOE BEND NB NorthCentral LEFT TURN LANE   NHPP $855 JUNE
   93  YV 198.0 F0031 TEGNER ST - WICKENBURG RANCH WAY NorthWest CONSTRUCT DIVIDED HIGHWAY   NHPP $41,000 JUNE
   85  MA 153.2 H8006 WARNER STREET BRIDGE SouthWest CONSTRUCT NEW BRIDGE   RARF $5,300 JUNE
 0000  MA PEO T0157 NEW RIVER - HAPPY VALLEY RD - PINNACLE PEAK RD Central MULTI-USE PATH     $585 JUNE
 0000  SC SSC T0232 SANTA CRUZ COUNTY ROAD IMPROVEMENT SouthCentral CHIP SEAL   CMAQ $794 JUNE 
 0000  MO KNG T0191 STOCKTON HILL ROAD SAFETY IMPROVEMENT CORRIDOR NorthWest CORRIDOR SAFETY COUNTERMEASURES   HSIP $639 JUNE
 0000  MA MAR T0221 SR 347 - SMITH ENKE - EDISON ROAD Central SIDEWALK PROJECT   STBG $280 JUNE
  347  MA 188.0 F0208 SR 347 & OLD MARICOPA ROAD INTERSECTION Central INSTALL TRAFFIC SIGNAL   HSIP $350 JUNE