Crews set final bridge girders on I-40/US 93 interchange in Kingman
Crews set final bridge girders on I-40/US 93 interchange in Kingman
Project to construct free-flowing interchange now 85% complete
KINGMAN – Crews have hoisted the final girders into place on a flyover bridge in Kingman as the Arizona Department of Transportation moves into the final months of a project to construct a free-flowing interchange between Interstate 40 and US 93, the future I-11.
This milestone comes as ADOT has reached 85% completion of a new $106 million interchange in Mohave County that will reduce delays on the main route between Phoenix and Las Vegas.
The 10 bridge girders make up two of seven spans on a bridge that will carry southbound US 93 traffic to eastbound I-40, eliminating the need for vehicles to stop at a traffic signal on Beale Street and I-40. The bridge sweeps above the westbound lanes of I-40 at Clack Canyon and is the project’s most visible structure.
The two recently installed spans are each roughly 160 feet long on a 43-foot-wide structure that’s about 1,100 feet long.
Crews will pour the bridge’s concrete deck in December.
Other project activities include ongoing pavement work on the mile-long ramps that will allow traffic to flow nonstop between I-40 and US 93. Crews are also working to widen the eastbound and westbound I-40 White Cliffs bridges, which are now 85% complete.
The ongoing construction will continue to involve daytime and nighttime work and lane restrictions. Throughout the project, drivers are able to continue exiting both US 93 and I-40 at Beale Street to access businesses, Route 66 and downtown Kingman.
Construction is expected to continue into spring 2027, when the interchange will open with 6 miles of widened or newly constructed roadway. The project includes four new bridges, two bridge widenings, four bridge rehabilitations and two miles of sound walls.
The project is creating a mile of new highway carrying traffic northwest of the existing interchange at I-40 and Beale Street. Other features include:
- Widening more than a mile of I-40 in both directions between the new interchange and Stockton Hill Road
- Adding a merge lane on US 93 northbound
- Widening and/or rehabilitating four bridges on I-40
- Building sound walls along a portion of I-40 to the west of Stockton Hill Road
- Constructing drainage features
ADOT began the project in July 2024.
For more information on the Kingman interchange project and to subscribe for updates, please visit azdot.gov/WestKingmanTI. The webpage includes a flyover video simulation of what the interchange will look like.