State Route 260 from Overgaard to US 60 Study

Overview

In 2010, the Arizona Department of Transportation, in coordination with the Federal Highway Administration and the Apache-Sitgreaves National Forest, completed an Initial Location / Design Concept Report on SR 260 from east of Overgaard at milepost 309.4 to the intersection of US 60 in Show Low at milepost 340.1. The Initial Location / Design Concept Report evaluated multiple alternatives to improve traffic flow and safety. Due to lack of funding, the project was canceled.

For more information please submit a public records request, referencing the above information and below project numbers:

ADOT Project Number: 260 NA 309 H7254 01L 

Federal Aid Project Number: STP 260 B(AWN) 

Timeline

September 2011

  • Produce the Draft Environmental Assessment.

Late Summer / Early Fall 2011

  • Hold public hearings.
  • Advertise the public meeting.
  • Produce the final Design Concept Report.

January 2012

  • Produce the final study document.