Timeline - Loop 303 from Interstate 10 to Proposed State Route 30
Study Timeline
- Draft Environmental Assessment and Design Concept Report - Spring 2018
- Public Hearing - Summer 2018
- Final Environmental Assessment and Design Concept Report - Fall 2018
- Final design and construction: Final design is scheduled to begin Summer 2021; construction start date has not been determined.