State Route 24 Interim Phase II: Ellsworth Road to Ironwood Drive

State Route 24 Interim Phase II: Ellsworth Road to Ironwood Drive

Contents

This project is complete

The Arizona Department of Transportation, in conjunction with the Federal Highway Administration, completed construction of the Interim Phase II section of State Route 24 (SR 24) also referred to as Gateway Freeway, in August 2022. This section includes approximately five miles of new freeway extending from Ellsworth Road in Maricopa County to Ironwood Drive in Pinal County. 

The Interim Phase II segment of SR 24 follows the completion of Phase I in 2014, which opened the segment of freeway between SR 202 (Loop 202/Santan Freeway) and Ellsworth Road.

Since the ultimate build-out of SR 24 is not anticipated until Phase V of the Maricopa Association of Governments’ Regional Transportation Plan, ADOT and FHWA have planned for an interim facility that will help serve the transportation needs of the region until additional funding is made available. The interim facility will preserve the access control plan for this corridor outlined in the 2011 Design Concept Report, and be built at-or-above grade throughout.

Project Elements

  • Two paved lanes in each direction separated by a graded median.
  • At-grade intersections at the following locations:
    • Williams Field Road
    • Signal Butte Road
    • Meridian Road
    • Ironwood Drive
  • Bridges over Ellsworth and Mountain roads
  • A drainage channel along the north side of the freeway.
  • Signage, traffic signals, lighting and pavement marking, as necessary.

SR 24 Area Map

 

SR24 map after opening between wlliams feld ironwood

 

What to expect next

  • Additional activities will continue for the next few months to complete minor work items, some of which may require lane restrictions.

Schedule

The schedule for this project is as follows:

  • Winter 2018: Contract awarded to design consultant
  • 2019 – 2020: Interim Phase II Final Design
  • Fall 2020: Construction begins
  • 2022: Construction completed (20-24 months duration)

Schedules are subject to change based on weather or other unforeseen factors.

Documents

Stay Informed 

...
  • Email: [email protected]
  • Phone: Call the ADOT Bilingual Project Information Line at 855.712.8530.
  • Mail: ADOT Communications, 1655 W. Jackson St., MD 126F, Phoenix, AZ 85007
  • Twitter:  Follow ADOT on Twitter  (@ArizonaDOT) for real-time highway conditions statewide.

Schedules are subject to change based on weather and other unforeseen factors.  Subscribe to receive project updates and traffic alerts by email. For more information, please call the ADOT Bilingual Project Information Line at 855.712.8530 or submit a question or comment by email.  For real-time highway conditions statewide, visit ADOT’s Traveler Information Site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except while driving