I-40 Cemetery Wash & Jackrabbit Road Bridge Rehabilitation
I-40 Cemetery Wash & Jackrabbit Road Bridge Rehabilitation
Contents
Project Cost: $3.9 million
Overview
The Arizona Department of Transportation has initiated a rehabilitation project on two bridges along Interstate 40: the Cemetery Wash Bridge (eastbound only) in Winslow (milepost 253) and the Jackrabbit Road Bridge near Joseph City (milepost 270).
Construction is scheduled to begin in spring 2026 and be completed by summer 2027 with a winter hiatus.
Project Elements
The project will include:
- Replacing each existing bridge deck surface with new pavement. The bridge deck is the top-riding surface of the bridge that motorists drive on.
- Installing new guardrail, pavement markings and other related work.
What to Expect During Construction
Traffic on I-40 will be reduced to one lane across the bridges during construction. Drivers should slow down and merge safely into the open lane.
Drivers need to be prepared to slow down and merge over safely when approaching the work zone, drive slowly through the work zone and use caution around construction personnel and equipment while the restrictions are in place.
ADOT will post information about traffic restrictions and closures as it becomes available. To receive traffic alerts and other updates by email, please subscribe here.
You can also stay informed of real-time, project-related traffic restrictions by visiting az511.gov or call 511, except while driving.
Schedules are subject to change because of weather or other unforeseen factors. Remember to slow down and use caution around construction workers and equipment.
Stay Informed

Subscribe to receive traffic alerts and project updates directly to your email.
- Email/Phone: Contact Community Relations Project Manager Ryan Harding at [email protected] or 602.550.8397.
- Teléfono: Línea Bilingüe de Información del Proyecto ADOT: 855.712.8530
- Mail: Write to Ryan Harding, ADOT Community Relations, 1655 W. Jackson St., MD 126F, Phoenix, AZ 85007.