The Arizona Department of Transportation is planning to install centerline rumble strips on US 93 approximately 38 miles northwest of Wickenburg (between mileposts 161-183). The purpose of the $545,000 safety improvement project is to reduce the frequency and severity of lane and road-departure crashes and includes the following:

  • Replacement of raised pavement markers.
  • Installation of new centerline pavement striping.
  • Pavement maintenance and crack-seal repair near the new rumble strips.

 

Project Area Map

US 93: Installation of Rumble Strips Project Map

Construction is anticipated to begin in summer 2022 with an expected duration of 60 calendar days. The project will occur within ADOT right-of-way and easements.

 

 

Traffic Alerts

...

ADOT will post information about lane restrictions or closures as it becomes available. If you would like to receive traffic alerts and other updates by email, please subscribe here.

Restrictions and Closures

Plan for overnight lane restrictions on US 93 north of Wickenburg July 18 - Aug. 5

Drivers should plan for up to 20-minute delays and allow extra travel time

The Arizona Department of Transportation advises drivers to plan for overnight lane restrictions on US 93 north of the town of Wickenburg while rumble strip installation is underway. The restrictions are scheduled nightly from 9 p.m. to 5 a.m. beginning Monday evening, July 18, through the morning of Friday, Aug. 5:

Motorist should expect delays up to 20 minutes while the following restrictions are in place:

  • US 93 will be narrowed to one lane only with alternating north- and southbound travel between the Santa Maria River and the junction with State Route 71 (mileposts 161 - 183). The lanes will be closed in 2-mile increments.
  • Flaggers and a pilot car will guide motorists through the work zone.
  • Law enforcement will be on site.
  • No weekend work is scheduled.

ADOT advises drivers to be prepared to stop in the work zone while the rumble strip installation is underway.

 


For information about project-related restrictions and closures please visit az511.gov or call 511, except while driving.

Schedules are subject to change because of weather or other unforeseen factors. Remember to slow down and use caution around construction workers and equipment.

 

Stay Informed:

...
  • EmailSubscribe to receive project updates and traffic alerts.
  • Phone: ADOT Project Information Line: 855.712.8530.
  • Teléfono: Línea de Información del Proyecto ADOT: 855.712.8530
  • Online: Submit a question or comment through the ADOT website. Visit azdot.gov/Contact and then select Projects from the dropdown menu.
  • Twitter: Follow ADOT on Twitter(@ArizonaDOT) for real-time highway conditions statewide.