This project is complete
Overview
Project Cost: $18.7 million
The Arizona Department of Transportation has completed a pavement project along a 12-mile section of US 93, roughly between the community of Nothing and State Route 97 (mileposts 144 to 156).
Project Area Map
The project scope includes:
- Removing and replacing the existing pavement, including the roadway shoulders and turn lanes.
- Paving the designated unpaved crossovers.
- Replacing the existing guardrail, embankment curb and fencing.
- Bridge deck joint repairs.
- Seeding, applying pavement markings, installing ground-in rumble strips and other related work.
What to expect during construction
- Intermittent daytime lane restrictions on north- and southbound US 93 from 6 a.m. to 6 p.m. Mondays through Thursdays, and 6 a.m. to noon on Fridays.
- Drivers should be prepared to slow down in the work zone and expect delays.
- One lane will remain open in each direction.
- Reduced speed limit in the work zones.
ADOT reminds drivers to be prepared to stop, proceed through the work zone with caution and watch for construction personnel and equipment while construction is underway.
Stay Informed of Restrictions and Closures
For real-time information about project-related restrictions and closures, please visit az511.gov or call 511, except while driving.
ADOT will provide more information about project schedules and potential traffic impacts as information becomes available. Stay informed of traffic restrictions before they occur by subscribing to GovDelivery and receive notifications sent directly to your email. It’s fast and easy! All we need is your email address.
Traffic Alerts
Plan for daytime restrictions on US 93 between Nothing and SR 97 through summer 2024 for roadway improvements
The Arizona Department of Transportation is initiating a construction project to improve the roadway along a 12-mile section of US 93, roughly between the community of Nothing and State Route 97 (mileposts 144 to 156).
Motorists should be prepared for the following restrictions to allow construction crews to remove and replace the existing guardrail from mileposts 151 to 153:
- Northbound US 93 will be narrowed to one lane from 6 a.m. Wednesday, April 12, through noon on Friday, April 28.
- Drivers should be prepared to slow down and stop in the work zone and expect delays.
- Reduced speed limit in the work zones.
- A 14-foot vehicle-width restriction will be in place.
The project elements include:
- Removing and replacing the existing pavement, including the roadway shoulders and turn lanes.
- Paving the designated unpaved crossovers.
- Replacing the existing guardrail, embankment curb and fencing.
- Bridge deck joint repairs.
- Seeding, applying pavement markings, installing ground-in rumble strips and other related work.
ADOT reminds drivers to be prepared to stop, proceed through the work zone with caution and watch for construction personnel and equipment while construction is underway.
Questions/Comments
ADOT welcomes your questions and comments. Please contact us in any of the following ways:
- Online: Submit a question or comment through the ADOT website. Visit azdot.gov/Contact and then select Projects from the dropdown menu.
- By phone: Call Michele Beggs, Community Relations Project Manager, at 928.566.5052.
- Teléfono: Línea de Información del Proyecto ADOT: 855.712.8530.
- By mail: Write to ADOT Community Relations, 3660 E. Andy Devine Ave. Kingman, AZ 86401