Learn more

Drivers should also expect lane restrictions on Salome Road beginning Aug. 29

The Arizona Department of Transportation advises drivers to plan for daytime lane restrictions on Salome Road in Tonopah beginning Friday, Aug. 29, and along eastbound Interstate 10 beginning Sept. 2.

The following lane restrictions will occur from 6 a.m. to 4 p.m. 

  • The north- and southbound Salome Road interchange will be reduced to one lane with alternating traffic control via a flagging operation Friday, Aug. 29, for guardrail repair. 

The following lane restrictions will occur overnight from 6 p.m. to 4 a.m. 

  • The north- and southbound Salome Road interchange will be reduced to one lane with alternating traffic control via a flagging operation Wednesday, Sept. 10, and Thursday, Sept. 11, for paving.  

The following I-10 lane restrictions are scheduled from 6 a.m. to 4 p.m., Tuesday, Sept. 2, through Friday, Sept. 12, for striping and delineator work. 

  • Eastbound I-10 between Salome Road and Tonopah (milepost 90) will be reduced to one lane. Note: Motorists should anticipate a 5-mile lane restriction while crews progress through the work zone.
  • A 12-foot vehicle width restriction will be in place. 
  • The speed limit will be reduced to 45 mph.

Delays are likely, so allow extra travel time. Proceed through the work zone with caution, slow down and watch for construction personnel and equipment.

Show less

Interstate 10, Salome Road to Tonopah Pavement Rehabilitation

Interstate 10, Salome Road to Tonopah Pavement Rehabilitation

Contents

Overview

The Arizona Department of Transportation and the Federal Highway Administration (FHWA) began a project late March 2025 to repair the pavement on Interstate 10 between Salome Road (milepost 80) and Tonopah (milepost 90).

The work consists of removing the existing pavement surface and replacing it with new asphalt concrete and other related work.

Project Fact Sheet

Project Area

Interstate 10, Salome Road to Tonopah Pavement Rehabilitation Project Area Map

Click to enlarge map.

Project Elements

  • Milling the existing pavement and replacing it with new asphalt.

  • Replacing guardrail and guardrail end terminals

  • Constructing drainage facilities

  • Bridge repairs and replacement of concrete bridge barrier

  • Replacing pavement markings, signage, and fencing

Project Schedule

  • Construction began in late March 2025 and is expected to take 11 months to complete.

  • To minimize traffic impacts, milling and paving work is tentatively scheduled to occur from 7 p.m. to 6 a.m. on weekdays. Other related work will take place during the day, which will require lane restrictions.

Stay Informed

...

Schedules are subject to change based on weather and other unforeseen factors. Subscribe to receive project updates and traffic alerts by email. For more information, please call the ADOT Bilingual Project Information Line at 855.712.8530 or at [email protected]. For real-time highway conditions statewide, visit ADOT’s Traveler Information Site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except while driving.

Pursuant to Title VI of the Civil Rights Act of 1964, the Americans with Disabilities Act (ADA) and other nondiscrimination laws and authorities, ADOT does not discriminate on the basis of race, color, national origin, sex, age, or disability. Persons that require a reasonable accommodation based on language or disability should contact Stephanie Dyer at [email protected] or 855.712.8530. Requests should be made as early as possible to ensure the State has an opportunity to address the accommodation.