State Route 85, Interstate 8 Thayer Road Drainage Improvements

State Route 85, Interstate 8 Thayer Road Drainage Improvements

Contents

This project is complete

Overview

project shotThe Arizona Department of Transportation improved drainage on State Route 85 near Gila Bend between milepost 1 and milepost 3. The consisted of making improvements to existing concrete box culverts at five locations.

Project Fact Sheet

Project Area Map

map State Route 85, Interstate 8 Thayer Road Drainage Improvements

Project Elements

  • Replaced existing pavement
  • Improved existing concrete box culverts at five locations
  • Removed existing guardrail and fence
  • Placed rip rap; a layer of large stones used to protect soil from erosion
  • Installed pavement markings

Project Schedule

The project began September 2024 and was completed May 2025.

Stay Informed

...

Schedules are subject to change based on weather and other unforeseen factors. Subscribe to receive project updates and traffic alerts by email. For more information, please call the ADOT Bilingual Project Information Line at 855.712.8530 or submit a question or comment by email. For real-time highway conditions statewide, visit ADOT’s Traveler Information Site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except while driving.