An update on the I-17 bridges in Munds Park

An update on the I-17 bridges in Munds Park

SR24-1

An update on the I-17 bridges in Munds Park

An update on the I-17 bridges in Munds Park

January 30, 2012

The northbound bridge is complete. Work on the southbound bridge (visible in this photo just behind the new bridge) will begin in the spring.

Last week we received a blog comment requesting an update on the I-17 bridges that span over Pinewood Boulevard in Munds Park. We thought it was a great suggestion and figured a blog post was in order!

But, first a little refresher …

You might remember we blogged about the bridges back in May. That’s when the first phase of construction was in full-swing and crews were working on the northbound bridge.

We told you then that this project is going to update the bridges initially built in 1958 … back when there wasn’t much development in the area. When the job is finished this fall, there will be two new bridges that will be long enough to accommodate today’s traffic levels and wide enough for a future third lane in each direction on I-17. The project also includes a new sidewalk on Pinewood Boulevard that will allow pedestrians to cross safely underneath I-17.

Where we’re at today

munds-park2

I-17 traffic over the new bridge.

The northbound bridge is complete and the project is in winter shutdown except for some electrical work being done.

Work on the southbound bridge will begin when the weather warms sufficiently in the spring.

When construction resumes, the southbound bridge will be demolished, then reconstructed and I-17 will be repaved through the work zone.

While this work is being done, the southbound bridge will be closed and motorists will be detoured over to the northbound lanes of I-17.

I-17 bridges in Munds Park ready for upgrades

I-17 bridges in Munds Park ready for upgrades

SR24-1

I-17 bridges in Munds Park ready for upgrades

I-17 bridges in Munds Park ready for upgrades

May 25, 2011

The bridges over Pinewood Boulevard in Munds Park have been carrying Interstate-17 traffic for the past 53 years and now it’s time for some well-deserved reconstruction!

ADOT has already begun the project that will rebuild the bridges and ramps on I-17 at Munds Park, an area just south of Flagstaff . Work started last month and is scheduled to wrap up by fall 2012.

When the job is finished, motorists will have two new bridges each measuring 100-feet long (they’re now just 25 feet). The bridges will also be wider to accommodate an eventual third lane planned for I-17. A new sidewalk on Pinewood Boulevard is going in, too. It will allow pedestrians to cross safely underneath I-17 (see above video).

This update is necessary because there is more traffic now then when the bridges were built in 1958. Back then there was no development in Munds Park . The bridges are just inadequate for today’s traffic.

Drivers should expect some slowing of traffic due to this project – especially over busy holiday weekends. It is expected that delays at peak holiday travel times could reach up to 45 minutes … so please plan accordingly.

Project Timeline

April 2011 - Oct. 2011: The northbound bridge will be demolished, then reconstructed and I-17 will be repaved through the work zone. Because the northbound bridge is closed, motorists traveling northbound on I-17 will be directed to a detour that crosses over the median and utilizes southbound lanes. All on and off ramps will remain open.

April 2012 - Oct. 2012: The southbound bridge will be demolished, then reconstructed and I-17 will be repaved through the work zone. While this work is being done, the southbound bridge will be closed and motorists will be detoured over to the northbound lanes of I-17.