US 89

US 89 landslide repair continues

US 89 landslide repair continues

SR24-1

US 89 landslide repair continues

US 89 landslide repair continues

September 3, 2014

By now, you know that crews on the US 89 project site near Page are busy blastingdigging and hauling dirt and rock – lots and lots of dirt and rock.

We’re talking roughly a million cubic yards of material which, as you can see in the video above, is being used to build a 1,400-foot-long buttress that will stabilize and reinforce the mountain slope that carries US 89.

Geotechnical Engineer Keith Dahlen explains that the construction activity recently triggered some movement of the original landslide and until work is complete there could be some additional settling of the slide.

“It’s nothing that we can’t control by getting that buttress put in place,” he says in the video.

Back to that recent movement – it happened last month and as a safety precaution, all workers were pulled off the site until everything was assessed. After geotechnical engineers inspected the site, work began again nearly 24 hours later. Throughout the duration of the project, the geological experts have been and will continue to closely monitor for any potential movement.

The ultimate repair of US 89, which is expected to be complete before next summer, is the final step in fulfilling ADOT’s three-pronged approach to the US 89 landslide incident. That approach included providing immediate emergency access, conducting a geotechnical investigation, and restoring essential traffic to the area, including the paving of US 89T (Navajo Route 20) to serve as a temporary detour until US 89 is reopened.

“This project is very important to those communities that weren’t able to benefit from the N 20 detour,” says ADOT Senior Deputy State Engineer Rob Samour in the video above. “We need to restore mobility to this area and US 89 is a critical link to that mobility.”

To see more of the project's progress, check out photos of the site on the ADOT Flickr page.

Check it Out: US 89 landslide blasting

Check it Out: US 89 landslide blasting

SR24-1

Check it Out: US 89 landslide blasting

Check it Out: US 89 landslide blasting

August 18, 2014

Shovels and wheelbarrows just aren’t going to cut it when you need to move nearly one million cubic yards of dirt and rocks

That’s why crews working to repair the landslide-damaged stretch of US 89 are using explosives.

As you can see in the video above, blasting is taking place above the slide. The excavated material will be trucked below to build a buttress (you can read our previous post for a more detailed look at the repair plan).

It probably goes without saying that these blasts were conducted by professionals, but we do want to mention that no one from our video team ventured near the site to get this footage. They were able to set up their trusty GoPro cameras well ahead of time and were not in the area during the blast.

If you’re interested in seeing how ADOT has used explosives on a different project, check out this post from 2011.

Long delays expected for northern Arizona drivers near Cameron

Long delays expected for northern Arizona drivers near Cameron

I-17 101 traffic interchange

Long delays expected for northern Arizona drivers near Cameron

Long delays expected for northern Arizona drivers near Cameron

August 5, 2014

PHOENIX – Drivers traveling US 89 near Cameron in northern Arizona should allow extra travel time, according to the Arizona Department of Transportation. A paving project along an eight-mile section (milepost 477-485) of US 89, about 60 miles north of Flagstaff, is causing delays.

Motorists may be delayed between 45 minutes to one hour. Flaggers will guide vehicles through the work zone. Restrictions are expected from 6 a.m. to 5 p.m. Wednesday, Aug. 6 and Thursday, Aug. 7 this week and Monday, Aug. 11 and Tuesday, Aug. 12 next week.

For the most current information about highway closures and restrictions statewide, visit ADOT’s Travel Information Site at www.az511.gov, follow us on Twitter (@ArizonaDOT) or call 5-1-1.

US 89 landslide repair update

US 89 landslide repair update

SR24-1

US 89 landslide repair update

US 89 landslide repair update

August 5, 2014
US 89 Landslide Repair (July 2014)

Crews have just started work to reconstruct the landslide-damaged portion of US 89 south of Page and, as you can see in the slideshow above, considerable progress has already been made.

Right now, crews are building access roads at the site prior to the start of heavy construction, which should begin later this month.

This project is a big one. It involves moving the roadway approximately 60 feet away from the landslide area toward Echo Cliffs and using rock material removed for the roadway realignment to construct a downslope buttress to stabilize the area.

ADOT continues work on US 89 widening, bridge replacement project near Cameron

ADOT continues work on US 89 widening, bridge replacement project near Cameron

SR24-1

ADOT continues work on US 89 widening, bridge replacement project near Cameron

ADOT continues work on US 89 widening, bridge replacement project near Cameron

July 22, 2014

According to Arizona’s Historic Bridge Inventory, the Cameron Truss Bridge was constructed in 1958 to replace another bridge that had been built back in 1911.

Here we are, 56 years later, and it’s time to replace that replacement…

“The current bridge is safe now, but it’s basically at the end of its lifespan,” says Project Supervisor Rick Schilke in the video above.

US 89 Cameron Roadway Improvements (June 2014)

The bridge has had a good run, though, and has carried countless vehicles over the Little Colorado River, near Cameron. It’s also kind of noteworthy, according to the bridge inventory.

“As a pivotal crossing on this regionally important route, the Cameron Truss Bridge enjoys a degree of historical significance for its contribution to northern Arizona transportation,” the document states on page 298. “The structure is technologically important as a well-preserved example of large-scale bridge construction.”

About the project

ADOT started in March on the project to expand US 89 from two lanes to four lanes through the community of Cameron within the Navajo Nation, approximately 50 miles north of Flagstaff. The project is planned to be constructed in two main phases, with completion expected in fall 2016.

Major work includes the widening of US 89 to two lanes in each direction between State Route 64 and the Little Colorado River (mileposts 464-467) and the removal and replacement of the existing Cameron Truss Bridge with two new bridges at that location.

Additional improvements include constructing a roundabout at the existing intersection of US 89 and SR 64, new sidewalks, streetlights and four pedestrian/livestock underpasses.

What drivers should expect

As Schilke explains in the video above, the restrictions to traffic will be relatively minor.

During the first phase of construction, all traffic will remain on its current alignment. For the second phase, all traffic will be moved onto the newly constructed roadway (anticipated in summer 2015).

Delays may occur during construction with traffic reduced to one lane. There will be directional signage and flaggers present during construction. ADOT advises motorists to be alert for construction equipment and personnel, and to proceed through the work zone with caution.

For more information, please check out the project Web page. If you’re interested in the history of the bridge (which we’re betting you are – you’re reading a transportation blog, after all!), you can find additional facts by viewing the Historic Bridge Inventory.

US 89 landslide repairs to begin later this month

US 89 landslide repairs to begin later this month

SR24-1

US 89 landslide repairs to begin later this month

US 89 landslide repairs to begin later this month

July 17, 2014

The truck to the left is capable of hauling about 23 cubic yards of material per load.

Try to visualize what one million cubic yards of rock and dirt amounts to…

That’s the quantity of material expected to be removed by crews as they work to repair US 89, the landslide-damaged highway just south of Page.

It’s hard to picture, isn’t it?

Help your imagination out by taking a look at the photo at right. We’re told these yellow trucks (the pickup truck on the right is there for scale) are capable of hauling about 23 cubic yards of material per load. So, with nearly one million cubic yards to move, it will take approximately 43,500 truckloads to finish the job … that’s a lot of rocks!

Work to start soon

Crews will begin moving those rocks very soon. The reconstruction of US 89 between Bitter Springs and Page is set to begin later this month. The State Transportation Board approved the $25 million project to repair the highway at their July 11 meeting in Cottonwood.

The roadway, which suffered catastrophic damage following a landslide on the early morning of Feb. 20, 2013, has remained closed after a 500-foot section of roadway buckled in Echo Cliffs, approximately 25 miles south of Page.

More about the necessary repairs

The project will include moving the roadway approximately 60 feet away from the landslide area toward Echo Cliffs and using rock material removed for the roadway realignment to construct a downslope buttress to stabilize the area.

The closed section of roadway is scheduled to reopen prior to next summer’s busy travel season. The construction contract will include a monetary incentive for the contractor if it is able to complete the project ahead of schedule.

Work on the project begins in a couple of weeks, but the major work is expected to start in late August when crews begin drilling and blasting operations to build the rock buttress.

The ultimate repair of US 89 is the final step in fulfilling ADOT’s three-pronged approach to the US 89 landslide incident, which included providing immediate emergency access, conducting a geotechnical investigation and restoring essential traffic to the area.

Last summer ADOT paved Navajo Route 20 (Temporary US 89), which was a mostly dirt road stretching from Bodaway-Gap to LeChee.

“Once a long-term solution was identified, ADOT worked diligently to complete all the federally required clearances needed prior to construction,” said Steve Boschen, ADOT deputy state engineer of project delivery. “This process can sometimes take years, but with help from many of our Navajo Nation partners, the Federal Highway Administration and other regulatory stakeholders, we are ready to begin the US 89 landslide repair.”

If you’ve been following along with us here on the blog, you’ll remember that ADOT has had several hurdles to clear up to this point. After an extensive geotechnical investigation identified the necessary repairs last summer, ADOT retained an engineering design firm and developed plans for the eventual repair. Following that, the team finalized all federally required environmental reviews that include cultural, biological and water quality measures, completed the plans for the required right-of-way easements, and finalized negotiations with the contractor.

The final step prior to last week’s board approval was completing negotiations on a guaranteed maximum price for the project construction with FNF Construction, the same contractor that completed the paving of US 89T.

The US 89 landslide repair project is eligible for reimbursement through the Federal Highway Administration’s emergency relief program, which provides funding to state and local agencies for the repair or reconstruction of highways, roads and bridges that are damaged in natural disasters and catastrophic failures.

US 89 landslide repairs to begin later this month

US 89 landslide repairs to begin later this month

I-17 101 traffic interchange

US 89 landslide repairs to begin later this month

US 89 landslide repairs to begin later this month

July 14, 2014

PHOENIX —The reconstruction of US 89 between Bitter Springs and Page will begin later this month after the State Transportation Board approved a $25 million project to repair the landslide-damaged highway at Friday’s board meeting in Cottonwood, according to the Arizona Department of Transportation.

The roadway, which suffered catastrophic damage following a landslide on the early morning of Feb. 20, 2013, has remained closed after a 500-foot section of roadway buckled in Echo Cliffs, approximately 25 miles south of Page.

The repair will include moving the roadway approximately 60 feet away from the landslide area toward Echo Cliffs and using rock material removed for the roadway realignment to construct a downslope buttress to stabilize the area.

The closed section of roadway is scheduled to reopen prior to next summer’s busy travel season. The construction contract will also include a monetary incentive for the contractor if it is able to complete the project ahead of schedule.

Work on the project will begin in a couple of weeks, but major work is expected to start in late August when crews begin drilling and blasting operations to build the rock buttress. Nearly 1 million cubic yards of rock material is expected to be removed and a 1,500-foot section of US 89 will be realigned with new pavement.

The ultimate repair of US 89 is the final step in fulfilling ADOT’s three-pronged approach to the US 89 landslide incident, which included providing immediate emergency access, conducting a geotechnical investigation and restoring essential traffic to the area.

Last summer ADOT paved Navajo Route 20 (Temporary US 89), which was a mostly dirt road stretching from Bodaway-Gap to LeChee.

“Once a long-term solution was identified, ADOT worked diligently to complete all the federally required clearances needed prior to construction,” said Steve Boschen, ADOT deputy state engineer of project delivery. “This process can sometimes take years, but with help from many of our Navajo Nation partners, the Federal Highway Administration and other regulatory stakeholders, we are ready to begin the US 89 landslide repair.”

Prior to breaking ground on the project later this month, ADOT had to clear several hurdles. After an extensive geotechnical investigation identified the necessary repairs last summer, ADOT retained an engineering design firm and developed plans for the eventual repair. Following that, the team finalized all federally required environmental reviews that include cultural, biological and water quality measures, completed the plans for the required right-of-way easements, and finalized negotiations with the contractor.

The final step prior to Friday’s board approval was completing negotiations on a guaranteed maximum price for the project construction with FNF Construction, the same contractor that completed the paving of US 89T.

The US 89 landslide repair project is eligible for reimbursement through the Federal Highway Administration’s emergency relief program, which provides funding to state and local agencies for the repair or reconstruction of highways, roads and bridges that are damaged in natural disasters and catastrophic failures.

ADOT selects preconstruction contractor for emergency repairs on US 89

ADOT selects preconstruction contractor for emergency repairs on US 89

I-17 101 traffic interchange

ADOT selects preconstruction contractor for emergency repairs on US 89

ADOT selects preconstruction contractor for emergency repairs on US 89

March 27, 2014

PHOENIX —The Arizona Department of Transportation cleared another hurdle this week in its effort to get the US 89 landslide repair started. ADOT has finalized an agreement with a contractor for preconstruction engineering services, which includes assistance with the final design and construction logistics for the ultimate fix.

Tempe-based FNF Construction, Inc. was selected by ADOT as the contractor for pre-construction services on the landslide-damaged highway that links Bitter Springs and Page.

FNF Construction is the same contractor ADOT successfully partnered with to complete the Temporary US 89 (US 89T) project, which now serves as the primary detour to and from the Page and Lake Powell areas. The previously unpaved Navajo Route 20 was paved in only three months to become US 89T, which opened to traffic in August.

Through a Construction-Manager-At-Risk contract, FNF Construction will work with the project design team. This early collaboration can lead to completing projects faster with reduced costs. Preconstruction services will also include the design of access roads at the project site that will be needed when construction starts as anticipated this summer.

“Every day, ADOT is getting closer to our goal of starting the US 89 landslide repair to reopen this roadway by the end of the year,” said Steve Boschen, ADOT deputy state engineer for design. “Using the Construction-Manager-At-Risk delivery method will ensure that we can optimize construction efficiency.”

The new preconstruction agreement with FNF Construction does not include the construction project to repair US 89. That contract is expected to be finalized later this spring.

The environmental and design process for a normal project can take two years to complete, but ADOT has been working with the Federal Highway Administration, Navajo Nation, Navajo Division of Transportation and the Bureau of Indian Affairs to expedite the environmental, utility and right-of-way clearance and approval processes, knowing the lack of a usable road between the Bitter Springs and Page communities is a hardship for many people.

Recently, ADOT received the necessary environmental and utility clearances on the ultimate repair of US 89. Without the clearances, ADOT cannot use federal funds for this repair project.

ADOT also continues to work with the Navajo Nation on obtaining the new right-of-way easements that will be necessary prior to construction. An agreement between the Federal Highway Administration, Navajo Nation and Bureau of Indian Affairs must be reached to establish an expanded easement that facilitates construction, as well as operations and maintenance, of the repaired roadway.

The repair is currently programmed at $25 million. The project will include moving the roadway approximately 60 feet toward Echo Cliffs and using that rock to construct a downslope buttress to stabilize the area.

 

ADOT begins work on US 89 widening project near Cameron

ADOT begins work on US 89 widening project near Cameron

I-17 101 traffic interchange

ADOT begins work on US 89 widening project near Cameron

ADOT begins work on US 89 widening project near Cameron

March 7, 2014

PHOENIX — The Arizona Department of Transportation has started a project to expand US 89 from two lanes to four lanes through the community of Cameron within the Navajo Nation, approximately 50 miles north of Flagstaff. 

Major work on the $36.7 million project includes widening US 89 to two lanes in each direction between State Route 64 and the Little Colorado River (mileposts 464-467) and removal and replacement of the existing US 89 Cameron Truss Bridge, which was built in 1959, with two new bridges at that location.

Additional improvements on US 89 through Cameron include constructing a roundabout at the existing intersection of US 89 and SR 64, new sidewalks, streetlights, and four pedestrian/livestock underpasses.

Construction is anticipated to be completed in two major phases with completion expected fall 2016.

Traffic delays may occur during construction with traffic reduced to one lane. There will be directional signage and flaggers present during construction. ADOT advises motorists to be alert for construction equipment and personnel, and to proceed through the work zone with caution.

US 89 is the primary travel route that connects Flagstaff, southern Utah, and the popular tourist destinations in the Page/Lake Powell region. US 89 between Bitter Springs and Page is currently closed due to the Feb. 20, 2013 landslide.

Motorists traveling on US 89 between Page and Flagstaff can bypass the landslide closure by using the newly paved, 44-mile-long US 89T route that runs parallel to US 89 from The Gap to LeChee. US 89T is the former Navajo Route 20 that connects with US 89 approximately 17 miles north of the US 160 junction (Tuba City exit).

With the reconstruction of the landslide-damaged portion of US 89 not expected to start until early this summer, ADOT, along with the Navajo Nation and Federal Highway Administration, pursued paving Navajo Route 20 (which became the US 89T route) to serve as a short-term solution.

To stay up-to-date with the latest highway conditions around the state, visit the ADOT Traveler Information Center at az511.gov or call 5-1-1.

Project to rebuild US 89 near Page moves forward

Project to rebuild US 89 near Page moves forward

I-17 101 traffic interchange

Project to rebuild US 89 near Page moves forward

Project to rebuild US 89 near Page moves forward

February 19, 2014

PHOENIX — One year after a landslide forced the closure US 89 south of Page, the Arizona Department of Transportation is gearing up to start construction early summer and potentially complete the emergency repair by the end of this year — if there are no environmental, utility or right-of-way hurdles.

Following an extensive geological investigation into the Feb. 20, 2013 landslide that concluded in July, ADOT has made major strides in accelerating progress on the emergency project.

Since August, ADOT has retained an engineering design firm and developed plans for the eventual repair; finalized all federally required environmental reviews that include cultural, biological and water quality measures; and completed the plans for the required right-of-way easements.

The environmental and design process for a normal project can take two years to complete, but ADOT has been working with the Federal Highway Administration, Navajo Nation, Navajo Division of Transportation and the Bureau of Indian Affairs to expedite the environmental, utility and right-of-way clearance and approval process, knowing the lack of a usable road between the Bitter Springs and Page communities is a hardship for many people.

ADOT passed a major milestone this week toward beginning construction on the ultimate repair of US 89. The final environmental documentation was submitted to the Federal Highway Administration today for review. Without this clearance, ADOT cannot use federal funds for this project. While that approval is pending, ADOT continues work on the pre-construction elements of the project, like finalizing the design of the repair.

ADOT also continues to work with the Navajo Nation on obtaining right-of-way easements that will be necessary prior to construction. An agreement between the Federal Highway Administration, Navajo Nation and Bureau of Indian Affairs must be reached to establish an expanded easement that facilitates construction, as well as operations and maintenance of the full repair.

“Our final goal for delivery of our three-pronged approach — which initially included the geotechnical investigation and providing emergency access, and restoring mobility to the region with the paving of Navajo Route 20 — is to complete the US 89 reconstruction by advancing the necessary environmental, utility and right of way clearances as diligently as possible while complying with all the regulations in conjunction with our Navajo Nation partners and other regulatory stakeholders,” said Jennifer Toth, ADOT state engineer and deputy director for transportation. “This project remains a top priority for ADOT and our project partners.”

The repair is currently estimated to cost $25 million. The project will include moving the roadway approximately 60 feet toward Echo Cliffs and using that rock to construct a downslope buttress to stabilize the area. ADOT wants to start the repairs as soon as possible following environmental, utility and right-of-way clearances.

Shortly after the landslide, ADOT, along with the Navajo Nation and the Federal Highway Administration, pursued paving Navajo Route 20 (which became the US 89T route) to serve as a short-term solution. By paving N20, the length of the originally established detour route (US 160 and State Route 98) was cut in half.

After three months of intensive work, the newly paved two-lane roadway was opened to traffic in August.

The US 89 emergency repair project is eligible for reimbursement through the Federal Highway Administration’s emergency relief program, which provides funding to state and local agencies for the repair or reconstruction of highways, roads and bridges that are damaged in natural disasters and catastrophic failures.