Interstate 40: Andy Devine Avenue Bridge Deck Replacement

Interstate 40: Andy Devine Avenue Bridge Deck Replacement

Contents

 

Project is on a hiatus, and will resume in spring 2024

 

Overview

Project Cost: $10.1 million

The Arizona Department of Transportation is working on a construction project to replace the deck on the I-40 Andy Devine Avenue Bridge (Exit 53) in east Kingman. A bridge deck is the surface of the bridge that motorists drive on.

Project Area Map

Interstate 40: Andy Devine Avenue Bridge Deck Replacement

 

Project Elements

Work includes:

  • Replacing the existing bridge deck on the westbound Andy Devine Avenue Bridge.
  • Replacing the bridge bearings, approach slabs, deck joint, and bridge-mounted sign structure.
  • Milling and paving the roadway, replacing curb and gutter and constructing and removing traffic-control crossovers.
  • Replacing guardrail and catch basins.
  • Installing new signage, striping and other related work.

What to expect during construction

Construction will be completed in two phases. In order to maintain traffic on I-40. Temporary travel lanes will be built to enable motorists to drive around the construction zone. The Andy Devine Avenue off- and on-ramps will remain open during construction.

  • Lane restrictions will be in effect throughout construction.
  • Motorists should be prepared for delays of up to 15 minutes.
  • The speed limit will be reduced in the work zone.

ADOT reminds drivers to proceed through the work zone with caution, slow down and watch for construction personnel and equipment while the lane restrictions are in place.

Project Schedule

This project is on a hiatus, and will resume in spring 2024.

Schedules are subject to change based on weather or other unforeseen factors. 

Restrictions and Closures

For information about project-related restrictions and closures please visit az511.gov or call 511, except while driving.

ADOT will provide updated information about project schedules and potential traffic impacts as information becomes available. Stay informed of traffic restrictions before they occur by subscribing to receive timely traffic alerts by email.

 

Traffic Alerts

...

Progress continues on the Interstate 40 Andy Devine Avenue Bridge Deck Replacement project

Drivers should use caution and allow extra travel time

The Arizona Department of Transportation is reminding Kingman-area drivers that restrictions are still in place as work progresses on the Interstate 40 Andy Devine Avenue Bridge Deck Replacement project in east Kingman.

Restrictions currently in place are:

  • Around-the-clock lane restrictions throughout construction.
  • Delays of up to 15 minutes.
  • Reduced speed limit in the work zone.

The I-40 off- and on-ramps at Andy Devine Avenue will remain open during construction, and construction is being done in two phases in order to maintain traffic on I-40.

The ongoing restrictions are needed for construction crews to safely complete the project, which includes:

  • Replacing the existing bridge deck on the westbound Andy Devine Avenue Bridge.
  • Replacing the bridge bearings, approach slabs, deck joint and bridge-mounted sign structure.
  • Milling and paving the roadway, replacing curb and gutter, and removing and replacing traffic-control crossovers.
  • Replacing guardrail and catch basins.
  • Installing new signage, striping and other related work.

The project is on schedule and anticipated to be completed this fall. For additional information, visit the project website.

...

Westbound I-40 on-ramp at Andy Devine Avenue in Kingman closed overnight June 7-8 for bridge work

Drivers should use caution and allow extra travel time


The Arizona Department of Transportation is advising Kingman-area drivers of the following upcoming restriction on Interstate 40 and Andy Devine Avenue in east Kingman as work continues on the bridge deck replacement project: 

  • The westbound I-40 on-ramp at Andy Devine Avenue (Exit 53) will be closed from 8 p.m. Wednesday, June 7, through 6 a.m. Thursday, June 8. 
    • Motorists can access westbound I-40 at Stockton Hill Road (Exit 51). 
  • Drivers should be prepared to slow down and stop in the work zone and expect delays. 
  • A 16-foot vehicle-width restriction will be in place.

The project elements include:

  • Replacing the existing bridge deck on the westbound Andy Devine Avenue Bridge. 
  • Replacing the bridge bearings, approach slabs, deck joint and bridge-mounted sign structure.
  • Milling and paving the roadway, replacing curb and gutter, and removing and replacing traffic-control crossovers.
  • Replacing guardrail and catch basins. 
  • Installing new signage, striping and other related work.

Construction is scheduled to be completed this fall. For additional information, visit the project website.

 

Stay Informed

...
  • By emailSubscribe to receive traffic alerts and project updates directly to your email.
  • Online: Submit a question or comment through the ADOT website. Visit azdot.gov/Contact and then select Projects from the dropdown menu.
  • By phone: Call the ADOT Bilingual Project Information Line at 855.712.8530.
  • Teléfono: Línea de Información del Proyecto ADOT: 855.712.8530
  • By mail: ADOT Community Relations, 3660 E. Andy Devine Ave. Kingman, AZ 86401.