Interstate 40: Topock - Needle Mountain Road Pavement Preservation
Interstate 40: Topock - Needle Mountain Road Pavement Preservation
Contents
This project is complete
The Arizona Department of Transportation has completed a project to replace pavement along 2.5 miles of Interstate 40 between the California state line at Topock and the Needle Mountain traffic interchange (mileposts 0 to 2).
Project Overview
Work included removing the existing top layer of pavement and replacing it with new pavement. The project also included making spot pavement repairs, replacing pavement markings and other related work.
Project Area Map
Project Schedule
Construction is finished.
Schedule subject to change based on weather or other unforeseen factors.
Restrictions and Closures
For real-time information about project-related restrictions and closures, please visit az511.gov or call 511, except while driving.
ADOT will provide more information about project schedules and potential traffic impacts as information becomes available. Stay informed of traffic restrictions before they occur by subscribing.
Traffic Alerts
The Arizona Department of Transportation is on target to complete the State Route 95 Needles Bridge Rehabilitation project in April.
The majority of the construction work has already been completed, including:
- Installing a new concrete bridge deck overlay to the existing bridge surface.
- Removing and replacing the pavement on the riding surface of the bridge.
- Replacing the bridge bearing pads and guardrail.
Remaining work includes reconstructing the southbound bridge approach and departure slabs, and applying the final lane striping.
Around-the-clock lane restriction on the State Route 95 Needles Bridge will continue to be in place through the end of construction in April.
ADOT advises drivers to slow down and use caution around personnel and equipment while construction is underway.
For additional information, visit the project website.
Stay Informed
ADOT welcomes your questions and comments. Please contact us in any of the following ways:
- Online: Submit a question or comment through the ADOT website. Visit azdot.gov/Contact and then select Projects from the dropdown menu.
- By phone: Call the ADOT Bilingual Project Information Line at 855.712.8530.
- Teléfono: Línea de Información del Proyecto ADOT: 855.712.8530.
- By mail: Write to ADOT Community Relations, 3660 E. Andy Devine Ave. Kingman, AZ 86401