Plan for overnight lane restriction on Irvington Road as an I-19 interchange improvements project begins in Tucson July 16

Learn more

Plan for overnight lane restriction on Irvington Road as an I-19 interchange improvements project begins in Tucson July 16

Drivers should expect delays and allow extra travel time

The Arizona Department of Transportation advises drivers to plan for overnight lane restrictions on Irvington Road between 12th Avenue and Calle Santa Cruz as a new interchange improvements project gets underway at Interstate 19 and Irvington Road in Tucson. 

Work is scheduled weekdays from 9 p.m. to 5 a.m. beginning Thursday, July 16, through spring 2028. 

Motorists can expect the following overnight restrictions :

  • East- and westbound Irvington Road will be narrowed to one lane in each direction. 
  • A 12-foot vehicle width restriction 
  • The speed limit will be reduced to 25 mph in the work zone

Drivers should allow extra travel time, use caution, be prepared to slow down and merge safely when approaching and traveling through all work zones.

street map with project area highlighted
Show less

I-19 Irvington Interchange Improvements Project

I-19 Irvington Interchange Improvements Project

Contents

Overview

The Arizona Department of Transportation is working to improve the Interstate 19 and Irvington Road interchange. The project will reconstruct the interchange to increase capacity and enhance safety by widening Irvington Road to three lanes in each direction and adding lanes to the I-19 on-ramps. The project is scheduled to begin construction in the summer of 2026.

Planned improvements include: 

  • Reconstructing the existing diamond interchange and adding a partial cloverleaf ramp at Irvington Road.
  • Widening on-ramps which will accommodate future ramp metering.
  • Installing traffic signals, lighting, signage and pavement markings.
  • Constructing pedestrian and bicycle facilities on both sides of Irvington Road.

Project Flyer

Project Area Map

Project Map - I-19 Irvington Traffic Interchange

Project Schedule

Construction is anticipated to start the summer of 2026 and is projected to take 20 months to complete, finishing up in the spring of 2028. Schedules are always subject to change because of weather and other unforeseen circumstances.

Traffic Restrictions

ADOT will maintain two lanes of travel in each direction on Irvington Road during the project.

Pre-work Photo Gallery

I-19 Irvington Rd Interchange Pre Construction 12/18/25

Pre-work Video Recording

Project Presentation

Stay Informed

...

ADOT welcomes your questions or comments. Please feel free to contact us in any of the following ways:

  • Online: Submit a question or comment through the ADOT projects email at: [email protected]
  • Email: Dulce Maria Rojo at [email protected]
  • By phone: Call the ADOT Bilingual Project Information Line at 855.712.8530.
  • By mail: Write to ADOT Communications and Public Involvement, 1221 S 2nd Ave. Tucson, AZ 85713.

For information about current project-related restrictions and closures, please visit az511.gov or call 511, except while driving.

ADOT will provide more information about project schedules and potential traffic impacts as information becomes available. Stay informed about traffic restrictions before they occur by signing up to receive timely traffic alerts by email. Please Subscribe to receive project updates and traffic alerts.