Project Spotlight: US 160 gets fresh pavement in Northeast Arizona
Project Spotlight: US 160 gets fresh pavement in Northeast Arizona
24 miles of pavement rehabilitated, other improvements made
DENNEHOTSO – US 160 in Northeastern Arizona now features fresh pavement due to an Arizona Department of Transportation project completed in partnership with the Navajo Nation.
The top layer of pavement was removed and replaced along 24 miles of US 160 between mileposts 416-440, improving the driving surface. Along with the pavement rehabilitation, crews made safety enhancements such as replacing guardrail, installing rumble strips, building up the shoulders, and paving turnouts off of the highway. Paving wrapped up with a chip seal treatment and new pavement markings.
Crews also replaced the existing bridge rail on the Walker Creek Bridge at milepost 435 with a more durable concrete barrier, enhancing driver safety. Additionally, erosion control measures were conducted near milepost 440.
Work on this $19.7 million project began in March 2025, with a brief break in construction during the winter. This project showcases ADOT’s commitment to protecting Arizona’s investment in highway pavement and bridges. ADOT is proud to provide an improved driving experience for drivers on this important route in Northeastern Arizona.
For more information, please visit the US 160 Dennehotso - MP 440 pavement rehabilitation project page at azdot.gov/projects > Northeast District