Timeline - SR 30: Loop 303 to Loop 202 Study.

  • Fall 2019 - Selected Alternative + Final EA & Location/Design Concept Report
  • May 2019 - Public Hearing
  • April 2019 - Draft Environmental Analysis & Initial Location/Design Concept Report
  • Jan. 2019 - Select Recommended Alternative
  • Nov. 2017 - Public Information Meeting (RBA and the No-Build Alternative)
  • Jan. 2015 - Public Open House (North, Center, Hybrid, South, and the No-Build Alternatives)
  • Mar. 2007 - Public Information Meeting (North, South, and the No-Build Alternatives)
  • Nov. 2006 - Study Newsletter (Expanded Study Corridors)
  • Mar. 2006 - Agency and Public Meetings (Study Corridors)
  • Sept. 2005 - Agency and Public Scoping Meetings (Study Area Only)
  • June 2005 - Study Begins