SR 95 Pavement Project: Courtwright Road - Bullhead Parkway

SR 95 Pavement Project: Courtwright Road - Bullhead Parkway

Contents

This project is complete

Overview

Project Cost: $26 million 

View Project Information Flyer

The Arizona Department of Transportation has completed construction to replace the riding surface along a 23-mile section of State Route 95, between Courtwright Road in Mohave Valley and Bullhead Parkway in Bullhead (mileposts 227 to 250).

SR95 Courtwright Rd Bullhead Pkwy Map

Work includes:

  • Removing the top layer of pavement and replacing it with new asphalt. 
  • Replacing curb and gutter, sidewalk ramps, pavement markings and other related work.

What to expect during construction

Lane restrictions will be limited to overnight hours only. No restrictions are anticipated to be in place during the day or weekends. Business access will be maintained during construction.

The restrictions include:

  • Overnight intermittent lane restrictions on north- and southbound SR 95 from 6 p.m. to 6 a.m. Sunday evenings through Friday mornings. 
  • Drivers should be prepared for delays up to 15 minutes.
  • One lane will remain open in each direction. 
  • The speed limit will be reduced in the work zones.

ADOT reminds drivers to proceed through the work zone with caution, slow down and watch for construction personnel and equipment while the restrictions are in place.

Project Schedule 

Work to remove and replace the sidewalk ramps took place during the summer. Paving started in October, and is expected to be finished in early 2024. 

Schedule subject to change based on weather or other unforeseen factors.

Traffic Alerts

...

Nighttime paving is underway on State Route 95 between Courtwright Road and Bullhead Parkway

Expect brief delays and allow extra travel time

FNF Paver image

Nighttime paving on State Route 95 is underway near Courtwright Road in Mohave Valley.

The Arizona Department of Transportation is reminding drivers in the Bullhead City area to prepare for overnight lane restrictions on State Route 95 as a new pavement project  is underway between Courtwright Road and Bullhead Parkway (mileposts 227-250).

Nighttime paving started this week near Courtwright Road (milepost 227). After the northbound lanes are completed, crews will pave the southbound lanes on the same segment of SR 95.

Motorists should allow extra travel time while the following nighttime restrictions are in place from 6 p.m. to 6 a.m. Sunday evenings through Friday mornings:

  • Portions of SR 95 will be narrowed to one lane within the project area. 
  • Flaggers and a pilot car will guide drivers through the work zone.

  • A 16-foot vehicle width restriction will be in place.

  • The speed limit will be reduced in the work zone.

  • Drivers should be prepared to come to a complete stop when approaching and driving through the work zone.

For additional information on the Courtwright Road - Bullhead Parkway project, visit the project webpage.

This is the first of two paving projects starting on SR 95. The second pavement project, which will be between Sara Park and Interstate 40 (mileposts 176 to 202)  is scheduled to start Sunday, July 9. ADOT will provide additional information on the second project as soon as construction information becomes available. For more information on the SR 95 Sara Park - Interstate 40 project, visit the project webpage.

Stay Informed of Restrictions and Closures

ADOT will provide more information about project schedules and potential traffic impacts as information becomes available. Stay informed of traffic restrictions before they occur by subscribing to GovDelivery and receive notifications sent directly to your email. It’s fast and easy! All we need is your email address. 

State Route 95 Pavement Project: Courtwright Road to Bullhead Parkway

For real-time information about project-related restrictions and closures, please visit az511.gov or call 511, except while driving

Questions/Comments

ADOT welcomes your questions and comments. Please contact us in any of the following ways:

  • Online: Submit a question or comment through the ADOT website. Visit azdot.gov/Contact and then select Projects from the dropdown menu.
  • By phone: Community Relations Project Manager Michele Beggs at 928.566.5052. 
  • Teléfono: Línea de Información del Proyecto ADOT: 855.712.8530.
  • By mail:  Write to ADOT Community Relations, 3660 E. Andy Devine Ave. Kingman, AZ 86401