ADOT uses new technique to ‘slide’ new I-40 Bellemont bridges into place

ADOT uses new technique to ‘slide’ new I-40 Bellemont bridges into place

I-17 101 traffic interchange

ADOT uses new technique to ‘slide’ new I-40 Bellemont bridges into place

ADOT uses new technique to ‘slide’ new I-40 Bellemont bridges into place

October 31, 2019

PHOENIX – A new technique that basically slides precast bridges into place has greatly reduced delays for the Bellemont community with an Arizona Department of Transportation project replacing spans over Interstate 40 at Transwestern Road west of Flagstaff.

Using this technique, which the contractor proposed, allowed crews to replace the bridges during a nine-day closure of Transwestern Road over I-40 rather than having the six to eight months of restrictions required for a traditional bridge replacement project.

Joining ADOT engineers in a process called value engineering, which analyzes plans looking for ways to improve quality and value while reducing time needed to complete improvements, the contractor proposed casting the new bridges whole to the east of the existing bridges and then moving them into place in a process that works much like sliding components into place. ADOT approved the plan.

Once the new bridges were complete, crews diverted I-40 traffic to the on- and off-ramps in order to demolish the old bridges. Workers then used hydraulic jacks to lift and move the new Bellemont/Transwestern Road bridges into place. That part of the process took about four-and-a-half days.

ADOT regularly looks for accelerated bridge construction methods and other innovations that can reduce delays and inconvenience for drivers. Earlier this year, for example, the agency used a process known as a geosynthetic reinforced soil-integrated bridge system to rebuild the bridges on I-40 at Meteor City Road, creating abutments by putting in alternating layers of granular fill reinforced with synthetic material. That process also cut construction time by months.

Simple, predictable schedule helping Pinto Creek bridge project

Simple, predictable schedule helping Pinto Creek bridge project

SR24-1

Simple, predictable schedule helping Pinto Creek bridge project

Simple, predictable schedule helping Pinto Creek bridge project

By Garin Groff / ADOT Communications
October 29, 2019

Let’s face it: Nobody looks forward to construction delays.

But with restrictions and some temporary closures set for the Pinto Creek Bridge replacement project on US 60 between Superior and Globe, we’re giving drivers something they can look forward to: a predicable schedule.

With a little planning now, you can avoid some frustration and save time.

Here’s what to plan for:

  • Daily lane restrictions begin Thursday (Oct. 31) and continue for several weeks Mondays through Thursdays between 6 a.m. and 4 p.m., and Fridays from 6 a.m. to noon.
  • Full closures are tentatively set to begin Thursday, Nov. 7. The closures will continue for several weeks on Tuesdays and Thursdays from 9 a.m. to 1 p.m. Drivers will detour on state routes 77 and 177 through Winkelman, adding at least 45 minutes of travel time between Globe and Superior.

While much of the construction will occur in Pinto Creek Canyon, we need the restrictions as crews continue building an access road into the canyon and removing rock to shift part of the highway about 30 feet. Crews will need to blast away some rock, which requires full highway closures for safety.

As we shared in an earlier news release, there is some encouraging news already: In the first few weeks, crews found the rock is softer than expected and can be removed with heavy equipment rather than by blasting. If that continues, we can reduce the number of full closures.

Additional restrictions and closures will come later in the project. They’ll include overnight closures to install bridge girders and pour the new structure’s concrete deck. Near the end of the project, we’ll need to close the road for about five days to shift the highway so it lines up with the new bridge.

Drivers will continue using the existing bridge until the new 695-foot-long structure is completed in about two years. When we're done, the new structure replacing a 70-year-old bridge will give motorists reliable transportation for decades to come.

Motorists can keep up to date on restrictions by subscribing for email updates at azdot.gov/PintoCreekBridge.

Pinto Creek Bridge replacement project underway on US 60

Pinto Creek Bridge replacement project underway on US 60

I-17 101 traffic interchange

Pinto Creek Bridge replacement project underway on US 60

Pinto Creek Bridge replacement project underway on US 60

October 3, 2019

PHOENIX – An Arizona Department of Transportation project on US 60 east of the Phoenix area is replacing the 70-year-old bridge over Pinto Creek with a nearly 700-foot span designed to better accommodate personal and commercial travel for decades to come. 

Traffic restrictions are scheduled to begin Monday, Oct. 7, on US 60 between Miami and Superior as construction gets underway on the two-year, $22.7 million Pinto Creek Bridge project.

Motorists should plan for lane restrictions and delays from 7 a.m. to 5 p.m. Monday through Wednesday, Oct. 7-9. The restrictions will allow crews to mobilize equipment and begin construction of an access road into Pinto Creek Canyon.

Additional restrictions and closures are tentatively scheduled to begin the week of Oct. 21. Lane restrictions are scheduled from 7 a.m. to 5 p.m. daily, with full closures of US 60 scheduled from 9 a.m. to 1 p.m. on Tuesdays and Thursdays. These restrictions and closures are expected to continue for about six to eight weeks.

During the full closures, which will allow crews to conduct blasting to move the highway about 30 feet to the north to align with the new bridge, motorists will detour on state routes 77 and 177 through Winkelman. This will add at least 45 minutes to the trip between the Globe area and Superior. Providing consistent days and times for these full closures is designed to help those relying on US 60 better schedule their travel between the Globe and Phoenix areas. 

Additional overnight closures are expected later in the project to place bridge girders and pour the concrete deck for the new bridge. Toward the end of the project, a five-day closure of US 60 will be required to finish realigning the highway with the new bridge.

The new bridge will be 695.5 feet length and supported by three piers. Being built adjacent to the current bridge, which will continue to be used during construction, it will have one lane of traffic in each direction and 8-foot-wide shoulders.

Once the bridge is completed, crews will dismantle the existing bridge, built in 1949 with an estimated lifespan of 50 years. While it remains safe for traffic, the existing bridge doesn’t meet current standards for bridge design used by ADOT, the Federal Highway Administration and the American Association of State Highway Transportation Officials.

For more information, please visit azdot.gov/PintoCreekBridge.

Federal grant will advance US 191 bridge improvements on Navajo Nation

Federal grant will advance US 191 bridge improvements on Navajo Nation

I-17 101 traffic interchange

Federal grant will advance US 191 bridge improvements on Navajo Nation

Federal grant will advance US 191 bridge improvements on Navajo Nation

September 10, 2019

PHOENIX – Winning a $10.4 million Federal Highway Administration grant will allow the Arizona Department of Transportation to advance improvements to four US 191 bridges in a corridor important to residents of the Navajo Nation and Hopi Reservation in northeastern Arizona.

The bridges cross major drainages on the Navajo Nation between Chinle Wash at milepost 470 north of Many Farms and Lukachukai Creek at milepost 488.

ADOT plans to use accelerated bridge construction methods on the project because of the economic importance of this stretch of US 191. This innovative approach reduces traffic impacts by shortening the time needed to improve each bridge while reducing the overall cost.

In applying for the Competitive Highway Bridge Program grant, ADOT bundled the four bridges under one project, which allows resources to be shared during construction. The agency’s application, developed in consultation with tribal leaders, noted the route’s importance to those who rely on it for access to education, employment and essential services.

The grant allows ADOT to use funds currently committed to this project to address other transportation needs in Arizona.

The Federal Highway Administration issued a total of $225 million in Competitive Highway Bridge Program grants to 18 states.

New methods mean getting I-40 bridge project done faster

New methods mean getting I-40 bridge project done faster

SR24-1

New methods mean getting I-40 bridge project done faster

New methods mean getting I-40 bridge project done faster

By Ryan Harding / ADOT Communications
August 6, 2019

If you travel east of Flagstaff along Interstate 40, you may have noticed crews hard at work building a new bridge at the Meteor City Road interchange. You might be thinking that this is going to take the better part of a year to get done.

Actually, by using new and innovative techniques ADOT intends to have this entire project, which started in mid-July and would ordinarily take six months or more, wrapped up this fall.

Crews are creating bridge abutments by putting in alternating layers of granular fill reinforced with synthetic material. This method is known as a geosynthetic reinforced soil-integrated bridge system, and it’s ADOT’s first use of this technique.

But wait, there’s more. A second first-time innovation being employed to build this bridge involves a new way to lay the bridge deck.

The deck will be constructed using a polyester polymer concrete that can be placed and cured in a matter of days rather than weeks. This type of deck provides similar performance with lower maintenance costs compared to a traditional concrete bridge deck.

This is not only a first for ADOT but for the state.

The Arizona Management System championed by Governor Ducey challenges ADOT and other state agencies to continuously improve their value to customers – in this case to the drivers and others who will benefit from a faster project that will yield lower maintenance costs through the years. This innovative approach is allowing us to do just that.

Innovative techniques making I-40 bridge replacement faster

Innovative techniques making I-40 bridge replacement faster

I-17 101 traffic interchange

Innovative techniques making I-40 bridge replacement faster

Innovative techniques making I-40 bridge replacement faster

August 5, 2019

PHOENIX – An Arizona Department of Transportation project replacing the Interstate 40 bridge at Meteor City Road is using innovative techniques that get the work done faster, limit inconvenience for motorists and reduce long-term maintenance costs.

This work, which began in mid-July, is creating abutments by putting in alternating layers of granular fill reinforced with synthetic material. It’s ADOT’s first use of this technique, known as a geosynthetic reinforced soil-integrated bridge system, to rebuild an overpass.

The approach makes it possible for a bridge replacement that ordinarily would take about six months to wrap up this fall.

Bridges constructed using this method have lower maintenance costs over their life spans and also fit more seamlessly into the roadway approaches, creating a smoother transition from road to bridge.

In addition, the project is constructing a new bridge deck using a polyester polymer concrete that can be placed and cured in a matter of days rather than weeks. This new type of deck provides similar performance with lower maintenance costs compared to a traditional concrete bridge deck.

This method of constructing bridge decks is not only a first for ADOT but for the state.

In addition to replacing the bridge, crews will also reconstruct the roadway approach to the bridge.

The current detour that takes I-40 traffic onto the Meteor City Road off- and on-ramps to move through the work zone will last through mid-August.

ADOT works to inform the public about planned highway restrictions, but there is a possibility that unscheduled closures or restrictions may occur. Weather can also affect a project schedule. To stay up to date with the latest highway conditions around the state, visit ADOT’s Arizona Traveler Information site at az511.gov or call 511.

ADOT improving the bridges along I-40 west of Meteor Crater

ADOT improving the bridges along I-40 west of Meteor Crater

I-17 101 traffic interchange

ADOT improving the bridges along I-40 west of Meteor Crater

ADOT improving the bridges along I-40 west of Meteor Crater

July 22, 2019

PHOENIX – Drivers heading along I-40 between Flagstaff and Winslow should slow down and expect delays while work is taking place. The ramp detour will remain in place 24 hours a day, seven days a week. The speed limit is reduced to 45 mph.

In addition to replacing the bridges, crews will also reconstruct the roadway approach to the bridges.

The current detour will last through mid-August while the project is anticipated to wrap up sometime in the fall.

ADOT works to inform the public about planned highway restrictions, but there is a possibility that unscheduled closures or restrictions may occur. Weather can also affect a project schedule. To stay up to date with the latest highway conditions around the state, visit ADOT’s Arizona Traveler Information site at az511.gov or call 511.

Independence for Maricopa drivers

Independence for Maricopa drivers

SR24-1

Independence for Maricopa drivers

Independence for Maricopa drivers

By Tom Herrmann / ADOT Communications
July 22, 2019

Drivers in Maricopa have something to celebrate: independence from sitting on State Route 347 waiting for trains to pass.

Last week, crews removed the barricades and welcomed the first vehicles on to a new overpass carrying drivers over Maricopa-Casa Grande Highway and the Union Pacific Railroad tracks.

Trains are important to Arizona’s economy. They move many goods around our state efficiently. The good people of Maricopa won’t dispute that.

ADOT and Maricopa worked long and hard for the overpass and independence from trains that cross SR 347 more than 60 times every day. A $15 million federal TIGER grant is helping pay for the $55 million project, as is a $14 million investment by Maricopa.

Even with traffic flowing on the new alignment of SR 347, we still have work to do. The original alignment of SR 347 will be changed to mesh with the new road. Cul-de-sacs will prevent vehicles from reaching the railroad tracks. Honeycutt Avenue will be extended to connect with the new alignment.

This project improving safety and mobility in a fast-growing community remains on track to wrap up by late this year.

 

Art of Transportation: Metal meerkats

Art of Transportation: Metal meerkats

SR24-1

Art of Transportation: Metal meerkats

Art of Transportation: Metal meerkats

By John Dougherty / ADOT Communications
July 19, 2019

It's not exactly "Meerkat Manor," but you can see how a photographer could easily think of those African mammals and their habit of standing sentry while looking at the top of the new bridge girders on Interstate 17 at Pinnacle Peak. 

These rebar facsimiles will also quickly disappear as the project to expand Pinnacle Peak over I-17 and rebuilt the interchange continues. You can see a more expansive view of what the girder installation looked like in the photo gallery below.


I-17 and Pinnacle Peak Road_070119

 

VIDEO: The logistics of a concrete deck pour

VIDEO: The logistics of a concrete deck pour

SR24-1

VIDEO: The logistics of a concrete deck pour

VIDEO: The logistics of a concrete deck pour

By David Rookhuyzen / ADOT Communications
July 12, 2019

Chances are if you don't work in highway construction you haven't spent that much time thinking about what goes into pouring a concrete deck for new bridges.

But if you've ever been curious at all, our video team recently put together this look at everything that goes into creating a new bridge deck, using footage mostly shot during recent work on an expanded Interstate 10 bridge over Jimmie Kerr Boulevard in Casa Grande.

Tidbits included in this video include the temperature that concrete needs to be kept at before being poured and exactly how much concrete can go into such a large project. There's a lot of logistics and planning that goes into these sorts of projects, so take a few moments to see what exactly goes into this type of work.

This project, which will expand I-10 to three lanes in each direction between Early Road and Interstate 8 in Casa Grande, along with similar work near Eloy, is expected to wrap up later this summer.